A group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less what was the actual strength of workers?

A

30 workers

B

40 workers

C

42 workers

D

36 workers

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will use the concept of work done by a group of workers over a period of time.

Step 1: Define the variables
Let the actual strength of the workers be x. This means there are x workers.

Step 2: Determine the total work done
The group of workers can complete the job in 120 days. Therefore, the total work W can be expressed as:
W=Number of workers×Number of days=x×120

Step 3: Analyze the scenario with additional workers
If there were 4 more workers, the number of workers would be x+4. The work could then be finished in 12 days less, which means it would take 12012=108 days.

Step 4: Express the total work with the additional workers
The total work done with the additional workers can also be expressed as:
W=(x+4)×108

Step 5: Set the two expressions for work equal to each other
Since the total work W is the same in both scenarios, we can set the equations equal to each other:
x×120=(x+4)×108

Step 6: Expand and simplify the equation
Expanding the right side:
120x=108x+432

Step 7: Rearrange the equation to isolate x
Subtract 108x from both sides:
120x108x=432
12x=432

Step 8: Solve for x
Now, divide both sides by 12:
x=43212=36

Conclusion
The actual strength of the workers is x=36.

|
Updated on:18/9/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?

    A17
    B24
    C30
    D22
  • Question 2 - Select One

    A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?

    A17
    B24
    C30
    D22
  • Question 3 - Select One

    A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?

    A50
    B40
    C56
    D58