A group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less what was the actual strength of workers?
30 workers
40 workers
42 workers
36 workers
The correct Answer is:D
To solve the problem step by step, we will use the concept of work done by a group of workers over a period of time.
Step 1: Define the variables
Let the actual strength of the workers be x. This means there are x workers.
Step 2: Determine the total work done
The group of workers can complete the job in 120 days. Therefore, the total work W can be expressed as:
W=Number of workers×Number of days=x×120
Step 3: Analyze the scenario with additional workers
If there were 4 more workers, the number of workers would be x+4. The work could then be finished in 12 days less, which means it would take 120−12=108 days.
Step 4: Express the total work with the additional workers
The total work done with the additional workers can also be expressed as:
W=(x+4)×108
Step 5: Set the two expressions for work equal to each other
Since the total work W is the same in both scenarios, we can set the equations equal to each other:
x×120=(x+4)×108
Step 6: Expand and simplify the equation
Expanding the right side:
120x=108x+432
Step 7: Rearrange the equation to isolate x
Subtract 108x from both sides:
120x−108x=432
12x=432
Step 8: Solve for x
Now, divide both sides by 12:
x=43212=36
Conclusion
The actual strength of the workers is x=36.
Let the actual strength of the workers be x. This means there are x workers.
The group of workers can complete the job in 120 days. Therefore, the total work W can be expressed as:
W=Number of workers×Number of days=x×120
If there were 4 more workers, the number of workers would be x+4. The work could then be finished in 12 days less, which means it would take 120−12=108 days.
The total work done with the additional workers can also be expressed as:
W=(x+4)×108
Since the total work W is the same in both scenarios, we can set the equations equal to each other:
x×120=(x+4)×108
Expanding the right side:
120x=108x+432
Subtract 108x from both sides:
120x−108x=432
12x=432
Now, divide both sides by 12:
x=43212=36
The actual strength of the workers is x=36.
Topper's Solved these Questions
Similar Questions
A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
View SolutionA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View Solution
Knowledge Check
- Question 1 - Select One
a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?
A17B24C30D22 - Question 2 - Select One
A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
A17B24C30D22 - Question 3 - Select One
A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?
A50B40C56D58
A certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View SolutionA certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished 11 days Earlier. How many persons were there when the work started?
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View SolutionA certain number of men can complete a job in 30 days. If there were 5 men more, it could be completed in 10 days less. How many men were in the beginning?
View Solution