A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?
25
50
75
can’t be determined
The correct Answer is:C
Step by step video, text & image solution for A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only (1)/(5)th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Topper's Solved these Questions
Similar Questions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?
View SolutionKarim can do 14 of a work in 5 days. How many days will he take to complete the work?
View Solution
Knowledge Check
35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is
A20B35C30D25A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?
Aa. 10%Bb. 1427%Cc. 20%Dd. can't be determinedA Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?
A10%B1427%C20%Dcan’t be determined
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View SolutionA contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?
View SolutionA company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution