A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
50
40
30
10
The correct Answer is:D
To solve the problem step by step, we can follow these steps:
Step 1: Determine the total work done in terms of laborers and days.
Let the total work be represented as W. If 30 laborers can complete the work in 20 days, we can express the total work as:
W=Number of laborers×Number of days=30×20=600 labor-days
Step 2: Calculate the work done by one laborer in one day.
If one laborer does x amount of work in one day, then the work done by 30 laborers in one day is:
Work done by 30 laborers in one day=30x
And over 20 days, the total work done is:
Total work=20×30x=600x
Since we know the total work W=600, we can set this equal to 600x:
600=600x⟹x=1
This means one laborer does 1 unit of work in one day.
Step 3: Set up the equation for completing the work in 15 days.
Now, we want to find out how many laborers n are needed to complete the same work W in 15 days. If we employ n additional laborers, the total number of laborers becomes 30+n. The work done by these laborers in one day is:
Work done by (30+n) laborers in one day=(30+n)×1=30+n
Over 15 days, the total work done will be:
Total work in 15 days=15×(30+n)
Step 4: Set the total work equations equal to each other.
We know the total work W=600, so we can set up the equation:
15×(30+n)=600
Step 5: Solve for n.
Now, we can simplify and solve for n:
30+n=60015=40
n=40−30=10
Conclusion:
The contractor would need to employ 10 more laborers to complete the work in 15 days.
---
Let the total work be represented as W. If 30 laborers can complete the work in 20 days, we can express the total work as:
W=Number of laborers×Number of days=30×20=600 labor-days
If one laborer does x amount of work in one day, then the work done by 30 laborers in one day is:
Work done by 30 laborers in one day=30x
And over 20 days, the total work done is:
Total work=20×30x=600x
Since we know the total work W=600, we can set this equal to 600x:
600=600x⟹x=1
This means one laborer does 1 unit of work in one day.
Now, we want to find out how many laborers n are needed to complete the same work W in 15 days. If we employ n additional laborers, the total number of laborers becomes 30+n. The work done by these laborers in one day is:
Work done by (30+n) laborers in one day=(30+n)×1=30+n
Over 15 days, the total work done will be:
Total work in 15 days=15×(30+n)
We know the total work W=600, so we can set up the equation:
15×(30+n)=600
Now, we can simplify and solve for n:
30+n=60015=40
n=40−30=10
The contractor would need to employ 10 more laborers to complete the work in 15 days.
Similar Questions
Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View SolutionTwenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View Solution
Knowledge Check
20 women can complete a piece of work in 7 days. If 8 more women are put on the job. In how many days will they complete the work?
A4.5 daysB5 daysC5.5 daysD4.5 daysTwenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
A11B22C33Dnone of theseA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
A60B80C20D25
A contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
View SolutionA contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?
View SolutionA contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b. 6 c. 7 d. 8
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution