A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b. 6 c. 7 d. 8
5
6
3
9
The correct Answer is:A
Step by step video, text & image solution for A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b. \ 6 c. 7 d. 8 by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind the schedule the work should have been finished? a. 5 b. 6 c. 7 d. 8
View SolutionA builder decided to build a farmhouse in 45 days. He employed 150 men in the beginning and120 more after 30 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b. 6 c. 7 d. 8
A5B6C3D9 - Question 2 - Select One
A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?
A1. 4 daysB2. 5 daysC3. 8 daysD4. 7 days - Question 3 - Select One
A builder decided to build a farmhouse in 20 days. He employed 40 men in the beginning and 20 more after 10 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?
A8B6C5D12
A builder decided to build a farmhouse in 45 days. He employed 106 men in the beginning and 53 more after 35 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behing schedule would it have been finished?
View SolutionA contractor undertakes to do a piece of work in 96 days. He engages 100 men at the begin ning. But in the 1/6 of the scheduled time, 1/7 of work is completed. How many additional men should be employed so that the work will be com pleted in time?
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View SolutionA contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? 1 b. 114 c. 134 d. 112
View Solution40 men can do a piece of work in a given time. If only 30 men be engaged, 6 more days are needed to complete the work. In how many days can 60 men do the work?
View Solution