A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b.  6 c. 7 d. 8

A

5

B

6

C

3

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b. \ 6 c. 7 d. 8 by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b.  6 c. 7 d. 8

    A5
    B6
    C3
    D9
  • Question 2 - Select One

    A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?

    A1. 4 days
    B2. 5 days
    C3. 8 days
    D4. 7 days
  • Question 3 - Select One

    A builder decided to build a farmhouse in 20 days. He employed 40 men in the beginning and 20 more after 10 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?

    A8
    B6
    C5
    D12