A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
16
15
20
25
The correct Answer is:C
To solve the problem step by step, we will follow the reasoning provided in the video transcript.
Step 1: Understand the total work and initial conditions
The contractor has 40 days to complete the work and has deployed 20 men.
Step 2: Calculate the total work done in 32 days
Since he realized 8 days before the scheduled time that 1/3 of the work was still to be done, it means he completed 2/3 of the work in the first 32 days.
Step 3: Determine the amount of work done by 20 men in 32 days
Let the total work be represented as W. The work done in 32 days by 20 men can be calculated as:
Work done=Number of men×Days=20 men×32 days
This means:
23W=20×32
23W=640
To find W, we can rearrange the equation:
W=640×32=960
Step 4: Calculate the remaining work
Since 1/3 of the work is still to be done, we can calculate:
Remaining work=13W=13×960=320
Step 5: Determine the remaining time
There are 8 days left to complete the remaining work.
Step 6: Calculate the number of men needed to complete the remaining work
Let X be the number of additional men required. The total number of men working now will be 20+X. The work done by these men in 8 days should equal the remaining work:
(20+X)×8=320
Step 7: Solve for X
Now we can solve the equation:
20×8+X×8=320
160+8X=320
Subtracting 160 from both sides gives:
8X=160
Dividing both sides by 8 gives:
X=20
Conclusion
The contractor needs to hire 20 more men to complete the work on time.
The contractor has 40 days to complete the work and has deployed 20 men.
Since he realized 8 days before the scheduled time that 1/3 of the work was still to be done, it means he completed 2/3 of the work in the first 32 days.
Let the total work be represented as W. The work done in 32 days by 20 men can be calculated as:
Work done=Number of men×Days=20 men×32 days
This means:
23W=20×32
23W=640
To find W, we can rearrange the equation:
W=640×32=960
Since 1/3 of the work is still to be done, we can calculate:
Remaining work=13W=13×960=320
There are 8 days left to complete the remaining work.
Let X be the number of additional men required. The total number of men working now will be 20+X. The work done by these men in 8 days should equal the remaining work:
(20+X)×8=320
Now we can solve the equation:
20×8+X×8=320
160+8X=320
Subtracting 160 from both sides gives:
8X=160
Dividing both sides by 8 gives:
X=20
The contractor needs to hire 20 more men to complete the work on time.
Topper's Solved these Questions
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)
55 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- THEORY OF EQUATIONSBOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)
20 Videos
- TIME, SPEED AND DISTANCEBOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)
10 Videos
Similar Questions
Knowledge Check
10 men can make a wall in 8 days. How many men required to complete the same work in half day
A80B100C120D160If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
A,21B20C24D22A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
A20B30C15D45
Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View Solution7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
View SolutionIf 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
View Solution