20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:28


To solve the problem, we can use the concept of work done, which is based on the formula:

Men×Days=Work

Given:
- 20 men can complete the work in 35 days.

We need to find out how many men (let's call this M2) are required to complete the same work in 25 days.

1. Calculate the total work done by the first group of men:
Work=Men×Days=20 men×35 days=700 man-days

2. Set up the equation for the second scenario:
We want to find M2 such that:
M2×25 days=700 man-days

3. Solve for M2:
M2=700 man-days25 days=28 men

4. Conclusion:
Therefore, 28 men are needed to complete the same work in 25 days.

Summary of the Solution:
- Total work: 700 man-days
- Men needed for 25 days: 28 men

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 10 men can make a wall in 8 days. How many men required to complete the same work in half day

    A80
    B100
    C120
    D160
  • 12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men are engaged in the same work ?

    A28
    B36
    C48
    D52
  • If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?

    A21
    B20
    C24
    D22