20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.
The correct Answer is:28
To solve the problem, we can use the concept of work done, which is based on the formula:
Men×Days=Work
Given:
- 20 men can complete the work in 35 days.
We need to find out how many men (let's call this M2) are required to complete the same work in 25 days.
1. Calculate the total work done by the first group of men:
Work=Men×Days=20 men×35 days=700 man-days
2. Set up the equation for the second scenario:
We want to find M2 such that:
M2×25 days=700 man-days
3. Solve for M2:
M2=700 man-days25 days=28 men
4. Conclusion:
Therefore, 28 men are needed to complete the same work in 25 days.
Summary of the Solution:
- Total work: 700 man-days
- Men needed for 25 days: 28 men
- 20 men can complete the work in 35 days.
Work=Men×Days=20 men×35 days=700 man-days
We want to find M2 such that:
M2×25 days=700 man-days
M2=700 man-days25 days=28 men
Therefore, 28 men are needed to complete the same work in 25 days.
- Total work: 700 man-days
- Men needed for 25 days: 28 men
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Foundation Level)
51 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)
37 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
Knowledge Check
10 men can make a wall in 8 days. How many men required to complete the same work in half day
A80B100C120D16012 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men are engaged in the same work ?
A28B36C48D52If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
A21B20C24D22
Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View SolutionIf 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
View SolutionIf 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
(a)60 men
(b)20 men
(c)50 men
(d)40 men
View Solution