A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?
80
81
82
83
The correct Answer is:B
Step by step video, text & image solution for A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Expert Level)27videos
TIME AND WORK
- BOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself15videos
SET THEORY
- BOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself15videos
TIME, SPEED AND DISTANCE
Similar Questions
A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 47 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? 80 b. 82 c. 81 d. 83
View SolutionA contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View Solution
Knowledge Check
- Question 1 - Select One
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A60B56C70D42 - Question 2 - Select One
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A35B40C45DNone of these - Question 3 - Select One
A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?
A162B234C262D81
A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 25 of the work is finished. How many additional men are be employed so that the work many be completed on time, each man now working 9 hours a day?
View SolutionA contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?
View SolutionA contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?View SolutionA contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?
View Solution7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
View Solution