A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
The correct Answer is:56
Step by step video, text & image solution for A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Topper's Solved these Questions
Similar Questions
A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 47 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? 80 b. 82 c. 81 d. 83
View SolutionA contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 25 of the work is finished. How many additional men are be employed so that the work many be completed on time, each man now working 9 hours a day?
View Solution
Knowledge Check
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A60B56C70D42A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?
A80B81C84D85A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A35B40C45DNone of these
A contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?
View SolutionA contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?
View SolutionA contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?
View SolutionA contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?
View Solution90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?
View Solution