A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
70
75
80
85
The correct Answer is:75
Step by step video, text & image solution for A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Related Playlists
Similar Questions
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View SolutionA contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
View SolutionA man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View Solution40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View SolutionA contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?View Solution20 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?
View Solution