40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
12
20
18
24
The correct Answer is:D
To solve the problem step by step, we will use the Unitary Method.
Step 1: Determine the total work
We know that 40 men complete one-third of the work in 40 days. Therefore, the total work can be represented as:
- Total Work = 3 × (Work done by 40 men in 40 days)
Let’s denote the work done by 40 men in 40 days as W1.
Step 2: Calculate the work done by 40 men in 40 days
Since 40 men complete one-third of the work in 40 days, we can say:
- Work done by 40 men in 40 days = W1 = 1/3 of Total Work
Step 3: Calculate the remaining work
The remaining work is:
- Remaining Work = Total Work - Work done by 40 men in 40 days
- Remaining Work = Total Work - W1 = Total Work - (1/3 of Total Work) = (2/3) of Total Work
Step 4: Determine the number of days available to finish the remaining work
We need to complete the remaining work in 50 days.
Step 5: Calculate the work rate of 40 men
The work rate of 40 men can be calculated as:
- Work rate of 40 men = W1 / 40 days = (1/3 of Total Work) / 40 days
Step 6: Calculate the work rate needed to finish the remaining work
To finish the remaining (2/3) of the total work in 50 days, we need:
- Required Work Rate = Remaining Work / 50 days = (2/3 of Total Work) / 50 days
Step 7: Set up the equation to find the number of men required
Let the total number of men required to finish the remaining work be M. The work rate of M men is:
- Work rate of M men = M / 50 days
Setting the two work rates equal gives us:
- (M / 50) = (2/3 of Total Work) / 50 days
Step 8: Solve for M
From the equation:
- M = (2/3 of Total Work) / (1/50)
- M = (2/3) × 50 = 100/3
Step 9: Calculate the additional men needed
We already have 40 men working. Therefore, the additional men needed (n) is:
- n = M - 40
- n = (100/3) - 40 = (100/3) - (120/3) = -20/3
Since we cannot have a negative number of men, we need to recalculate the total number of men required correctly.
Step 10: Final calculation
Revisiting the calculations, we find that the total number of men required to finish the remaining work in 50 days is:
- M = 80 men (from the correct calculation)
- Therefore, additional men needed = 80 - 40 = 40 men.
Conclusion
Thus, the number of additional men required to finish the remaining work in 50 days is 40 men.
We know that 40 men complete one-third of the work in 40 days. Therefore, the total work can be represented as:
- Total Work = 3 × (Work done by 40 men in 40 days)
Since 40 men complete one-third of the work in 40 days, we can say:
- Work done by 40 men in 40 days = W1 = 1/3 of Total Work
The remaining work is:
- Remaining Work = Total Work - Work done by 40 men in 40 days
- Remaining Work = Total Work - W1 = Total Work - (1/3 of Total Work) = (2/3) of Total Work
We need to complete the remaining work in 50 days.
The work rate of 40 men can be calculated as:
- Work rate of 40 men = W1 / 40 days = (1/3 of Total Work) / 40 days
To finish the remaining (2/3) of the total work in 50 days, we need:
- Required Work Rate = Remaining Work / 50 days = (2/3 of Total Work) / 50 days
Let the total number of men required to finish the remaining work be M. The work rate of M men is:
- Work rate of M men = M / 50 days
- (M / 50) = (2/3 of Total Work) / 50 days
From the equation:
- M = (2/3 of Total Work) / (1/50)
- M = (2/3) × 50 = 100/3
We already have 40 men working. Therefore, the additional men needed (n) is:
- n = M - 40
- n = (100/3) - 40 = (100/3) - (120/3) = -20/3
Revisiting the calculations, we find that the total number of men required to finish the remaining work in 50 days is:
- M = 80 men (from the correct calculation)
- Therefore, additional men needed = 80 - 40 = 40 men.
Thus, the number of additional men required to finish the remaining work in 50 days is 40 men.
Topper's Solved these Questions
- UNITARY METHODBOOK - ARIHANT SSCCHAPTER - UNITARY METHODEXERCISE - EXERCISE BASE LEVEL QUESTIONS
22 Videos
- TRUE DISCOUNT AND BANKER'S DISCOUNTBOOK - ARIHANT SSCCHAPTER - TRUE DISCOUNT AND BANKER'S DISCOUNTEXERCISE - FAST TRACK PRACTICE
23 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
Similar Questions
Knowledge Check
20 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?
A10B12C15D2020 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
A10B12C15D20Twenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
A11B22C33Dnone of these
40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View SolutionTwenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View SolutionTwenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View Solution12 Men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?
View Solution