A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work finished one day earlier.How many days would it have been delayed if 5 more men were not employed?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:1


To solve the problem step by step, let's break it down:

Step 1: Calculate the total work in man-days
The total work required can be calculated by multiplying the number of men by the number of days they are supposed to work.

Total work=Number of men×Number of days=30 men×38 days=1140 man-days

Step 2: Calculate the work done in the first 25 days
In the first 25 days, the 30 men would have completed:

Work done in 25 days=30 men×25 days=750 man-days

Step 3: Calculate the remaining work
The remaining work after 25 days is:

Remaining work=Total workWork done in 25 days=1140 man-days750 man-days=390 man-days

Step 4: Calculate the number of men after 25 days
After 25 days, 5 more men were employed, making the total number of men:

Total men after 25 days=30+5=35 men

Step 5: Calculate the time taken to finish the remaining work with 35 men
Now, we need to find out how many days it takes for 35 men to complete the remaining 390 man-days of work:

Days required=Remaining workNumber of men=390 man-days35 men11.14 days

Since the work finished one day earlier than the planned 38 days, it means they actually took:

381=37 days

Step 6: Calculate the total days taken without the additional men
If the additional 5 men were not employed, the remaining work would have to be done by the original 30 men. We calculate how many days it would take for 30 men to finish the remaining 390 man-days:

Days required without extra men=390 man-days30 men=13 days

Step 7: Calculate the total days taken without the additional men
If they had taken 13 days to finish the remaining work after the initial 25 days, the total days taken would be:

Total days without extra men=25+13=38 days

Step 8: Calculate the delay
Now, we compare this with the original plan of 38 days. Since they finished in 38 days without the additional men, there would be no delay.

Conclusion
If 5 more men were not employed, the work would not have been delayed.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? 1 b.  114 c. 134 d. 112

    A1 day
    B1 1/4 days
    C1 3/4 days
    D1 1/2 days
  • Question 2 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5
  • Question 3 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finIsh the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5