A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?
80
81
84
85
The correct Answer is:81
To solve the problem step by step, we need to determine how many additional men are required to complete the remaining work in the given time, with the new working hours.
Step 1: Calculate the total work
The total work can be represented as 1 unit of work.
Step 2: Determine the work completed
After 33 days, 47 of the work is completed. Therefore, the remaining work is:
Remaining Work=1−47=37
Step 3: Calculate the work done in 33 days
117 men working for 8 hours a day for 33 days can be calculated as:
Work done=Number of men×Hours per day×Days
Work done=117×8×33
Step 4: Calculate the total work in terms of units
Since 47 of the work is done, we can express the total work in units:
Total Work=117×8×3347=117×8×33×74
Step 5: Calculate the remaining time
The total time for the contract is 46 days. After 33 days, the remaining time is:
Remaining Days=46−33=13 days
Step 6: Calculate the work that needs to be done in the remaining time
We need to complete 37 of the total work in the remaining 13 days, with each man now working 9 hours a day.
Step 7: Calculate the total work required in the remaining time
The work that needs to be completed can be expressed as:
Remaining Work=37×Total Work
Step 8: Set up the equation for the remaining work
Let x be the number of additional men required. The total number of men working now will be 117+x. The work done by 117+x men in 13 days working 9 hours a day is:
(117+x)×9×13
Step 9: Equate the work done to the remaining work
We set up the equation:
(117+x)×9×13=37×117×8×33×74
Step 10: Solve for x
1. Calculate the right side of the equation.
2. Simplify and solve for x.
After performing the calculations, we find:
198=117+x
x=198−117=81
Final Answer
The number of additional men required is 81.
---
The total work can be represented as 1 unit of work.
After 33 days, 47 of the work is completed. Therefore, the remaining work is:
Remaining Work=1−47=37
117 men working for 8 hours a day for 33 days can be calculated as:
Work done=Number of men×Hours per day×Days
Work done=117×8×33
Since 47 of the work is done, we can express the total work in units:
Total Work=117×8×3347=117×8×33×74
The total time for the contract is 46 days. After 33 days, the remaining time is:
Remaining Days=46−33=13 days
We need to complete 37 of the total work in the remaining 13 days, with each man now working 9 hours a day.
The work that needs to be completed can be expressed as:
Remaining Work=37×Total Work
Let x be the number of additional men required. The total number of men working now will be 117+x. The work done by 117+x men in 13 days working 9 hours a day is:
(117+x)×9×13
We set up the equation:
(117+x)×9×13=37×117×8×33×74
1. Calculate the right side of the equation.
2. Simplify and solve for x.
198=117+x
x=198−117=81
The number of additional men required is 81.
Topper's Solved these Questions
Similar Questions
A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 47 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? 80 b. 82 c. 81 d. 83
View SolutionA contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View Solution
Knowledge Check
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A60B56C70D42A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A35B40C45DNone of theseA contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?
A162B234C262D81
A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 25 of the work is finished. How many additional men are be employed so that the work many be completed on time, each man now working 9 hours a day?
View SolutionA contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?
View SolutionA contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?
View SolutionA contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?
View Solution7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
View Solution