90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?

A

10

B

15

C

20

D

25

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will use the concept of work done, which is based on the number of men, the number of days, and the total work.

Step 1: Understand the total work and the work done in the given time.
- Total work (W) can be calculated based on the initial information. If 90 men can complete the work in 40 days, the total work can be expressed as:
W=Men×Days=90×40=3600 man-days

Step 2: Calculate the work done in 25 days.
- In 25 days, it is given that 23 of the work is completed. Therefore, the work done in 25 days is:
W1=23×3600=2400 man-days

Step 3: Determine the remaining work.
- The remaining work W2 can be calculated as:
W2=WW1=36002400=1200 man-days

Step 4: Calculate the remaining days to complete the work.
- Since 25 days have already been used, the remaining days D2 to finish the work is:
D2=4025=15 days

Step 5: Set up the equation for the remaining work.
- Let x be the number of men who will go off. The number of men remaining will be 90x. The equation for the remaining work can be set up as:
(90x)×15=1200

Step 6: Solve for x.
1. Expand the equation:
135015x=1200
2. Rearranging gives:
9015x=1200
3. Now, isolate x:
15x=901200
15x=1110
x=111015=74

Step 7: Conclusion.
- Therefore, the number of men that should be allowed to go off is:
x=74

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

    A60
    B56
    C70
    D42
  • A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?

    A162
    B234
    C262
    D81
  • A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?

    A495
    B514
    C528
    D532