It is given that 16men working 18hr per day can build a wall 36m long, 4m broad and 24m high in 20 days . How many men will be required to build a wall 64 m long 6m broad and 18m high working 12hr per day in 16 days ?

A

60

B

20

C

30

D

35

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will use the concept of work done, which can be calculated as the product of the number of men, the number of hours they work per day, and the number of days they work.

Step 1: Calculate the total work done in the first case
The total work done can be calculated using the formula:
Work=Length×Breadth×Height

For the first wall:
- Length = 36 m
- Breadth = 4 m
- Height = 24 m

So, the total work done (W1) is:
W1=36×4×24

Step 2: Calculate the total work done in the first case
Now, let's calculate W1:
W1=36×4×24=3456m3

Step 3: Calculate the total man-hours in the first case
The total man-hours can be calculated as:
Total Man-Hours=Number of Men×Hours per Day×Days

For the first case:
- Number of Men (M1) = 16
- Hours per Day (D1) = 18
- Days (T1) = 20

So, the total man-hours (M1) is:
M1=16×18×20

Step 4: Calculate the total man-hours in the first case
Now, let's calculate M1:
M1=16×18×20=5760man-hours

Step 5: Calculate the work done per man-hour
Now, we can find the work done per man-hour in the first case:
Work per Man-Hour=W1M1=34565760

Step 6: Calculate the work done per man-hour
Now, let's calculate:
Work per Man-Hour=34565760=0.6m3/man-hour

Step 7: Calculate the total work required for the second wall
For the second wall:
- Length = 64 m
- Breadth = 6 m
- Height = 18 m

So, the total work required (W2) is:
W2=64×6×18

Step 8: Calculate the total work required for the second wall
Now, let's calculate W2:
W2=64×6×18=6912m3

Step 9: Calculate the total man-hours available in the second case
For the second case:
- Hours per Day (D2) = 12
- Days (T2) = 16

Now, we need to find the total man-hours (M2):
M2=Number of Men×12×16

Step 10: Set up the equation to find the number of men required
Let the number of men required be x. Then:
x×12×16=Total Work Required

Step 11: Substitute the values and solve for x
Using the work done per man-hour:
x×12×16=6912
x×192=6912
x=6912192

Step 12: Calculate the number of men required
Now, let's calculate:
x=36

Final Answer
The number of men required to build the second wall is 36 men.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day?

    A16
    B20
    C30
    D10
  • Question 2 - Select One

    8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day?

    A16
    B20
    C30
    D10
  • Question 3 - Select One

    If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m?

    A30
    B10
    C18
    D28