It is given that 16men working 18hr per day can build a wall 36m long, 4m broad and 24m high in 20 days . How many men will be required to build a wall 64 m long 6m broad and 18m high working 12hr per day in 16 days ?
60
20
30
35
The correct Answer is:A
To solve the problem step by step, we will use the concept of work done, which can be calculated as the product of the number of men, the number of hours they work per day, and the number of days they work.
Step 1: Calculate the total work done in the first case
The total work done can be calculated using the formula:
Work=Length×Breadth×Height
For the first wall:
- Length = 36 m
- Breadth = 4 m
- Height = 24 m
So, the total work done (W1) is:
W1=36×4×24
Step 2: Calculate the total work done in the first case
Now, let's calculate W1:
W1=36×4×24=3456m3
Step 3: Calculate the total man-hours in the first case
The total man-hours can be calculated as:
Total Man-Hours=Number of Men×Hours per Day×Days
For the first case:
- Number of Men (M1) = 16
- Hours per Day (D1) = 18
- Days (T1) = 20
So, the total man-hours (M1) is:
M1=16×18×20
Step 4: Calculate the total man-hours in the first case
Now, let's calculate M1:
M1=16×18×20=5760man-hours
Step 5: Calculate the work done per man-hour
Now, we can find the work done per man-hour in the first case:
Work per Man-Hour=W1M1=34565760
Step 6: Calculate the work done per man-hour
Now, let's calculate:
Work per Man-Hour=34565760=0.6m3/man-hour
Step 7: Calculate the total work required for the second wall
For the second wall:
- Length = 64 m
- Breadth = 6 m
- Height = 18 m
So, the total work required (W2) is:
W2=64×6×18
Step 8: Calculate the total work required for the second wall
Now, let's calculate W2:
W2=64×6×18=6912m3
Step 9: Calculate the total man-hours available in the second case
For the second case:
- Hours per Day (D2) = 12
- Days (T2) = 16
Now, we need to find the total man-hours (M2):
M2=Number of Men×12×16
Step 10: Set up the equation to find the number of men required
Let the number of men required be x. Then:
x×12×16=Total Work Required
Step 11: Substitute the values and solve for x
Using the work done per man-hour:
x×12×16=6912
x×192=6912
x=6912192
Step 12: Calculate the number of men required
Now, let's calculate:
x=36
Final Answer
The number of men required to build the second wall is 36 men.
The total work done can be calculated using the formula:
Work=Length×Breadth×Height
- Length = 36 m
- Breadth = 4 m
- Height = 24 m
W1=36×4×24
Now, let's calculate W1:
W1=36×4×24=3456m3
The total man-hours can be calculated as:
Total Man-Hours=Number of Men×Hours per Day×Days
- Number of Men (M1) = 16
- Hours per Day (D1) = 18
- Days (T1) = 20
M1=16×18×20
Now, let's calculate M1:
M1=16×18×20=5760man-hours
Now, we can find the work done per man-hour in the first case:
Work per Man-Hour=W1M1=34565760
Now, let's calculate:
Work per Man-Hour=34565760=0.6m3/man-hour
For the second wall:
- Length = 64 m
- Breadth = 6 m
- Height = 18 m
W2=64×6×18
Now, let's calculate W2:
W2=64×6×18=6912m3
For the second case:
- Hours per Day (D2) = 12
- Days (T2) = 16
M2=Number of Men×12×16
Let the number of men required be x. Then:
x×12×16=Total Work Required
Using the work done per man-hour:
x×12×16=6912
x×192=6912
x=6912192
Now, let's calculate:
x=36
The number of men required to build the second wall is 36 men.
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION16videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION16videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE111videos
VOLUME AND SURFACE AREA
- BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)7videos
WORK AND WAGES
Similar Questions
Four persons can build a wall in 12 days . How many persons will be required to build the same will in 8 days.
View Solution15 men can build a 16.25 -m- long wall up to a certainj height in one day. How many men should be employed to build a wall of the same height but of length 26 metres in one day?
View Solution
Knowledge Check
- Question 1 - Select One
8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day?
A16B20C30D10 - Question 2 - Select One
8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day?
A16B20C30D10 - Question 3 - Select One
If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m?
A30B10C18D28
A tank is 8m long, 6m broad and 2m high. How much water can it contain?
View Solution40 men can build a wall 20 m high in 15 days. The number of men required to build a similar wall 25 m high in 6 days will be:
View Solution40 men build a well 20 m high in 15 days. The number of men required to build a similar wall 25 m high in 6 days will be:
View Solution36 men can build a wall 140 m long in 21 days , in how many days would 15 men be able to construct a similar wall 50 m long ?
View SolutionIf 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m?
View Solution