36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time?
16
18
20
22
The correct Answer is:B
Step by step video, text & image solution for 36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Topper's Solved these Questions
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
Similar Questions
A certain work is to be finished in a month, 12 worker appointed upon it could finished one-third of the work only in 12 days. How many additional workers must be employed to finish to the work in time?
View SolutionA man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View Solution
Knowledge Check
90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?
A10B15C20D2540 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D2420 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?
A10B12C15D20
20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View Solution100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View SolutionA contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?
View Solution