16 children and 24 men complete a certain workin 18days. If each child takes twice the time taken by a man to finish the work, in how many days will 24 men finish the same work?
12 days
24 days
36 days
48 days
The correct Answer is:B
To solve the problem step-by-step, we need to analyze the given information and apply the concepts of work and time.
Step 1: Understand the Work Done by Children and Men
We know that 16 children and 24 men complete a certain work in 18 days.
Step 2: Establish the Relationship Between the Time Taken by Children and Men
It is given that each child takes twice the time taken by a man to finish the work. Therefore, if we denote the time taken by a man to complete the work as T, then the time taken by a child will be 2T.
Step 3: Determine the Efficiency Ratio
Since work is inversely proportional to time, the efficiency ratio of children to men can be established as follows:
- If one man's efficiency is M, then one child's efficiency will be M2 because a child takes twice as long.
Thus, the efficiency ratio of children to men is:
Efficiency of 1 child=M2,Efficiency of 1 man=M
This gives us the ratio:
Efficiency of 1 childEfficiency of 1 man=12
Step 4: Calculate Total Efficiency of Children and Men
Now, we can calculate the total efficiency of 16 children and 24 men:
- Total efficiency of 16 children = 16×M2=8M
- Total efficiency of 24 men = 24×M=24M
Adding these together:
Total efficiency=8M+24M=32M
Step 5: Calculate Total Work Done
The total work done can be calculated using the formula:
Total Work=Total Efficiency×Time
Substituting the values we have:
Total Work=32M×18=576M
Step 6: Calculate the Time Taken by 24 Men to Complete the Same Work
Now, we need to find out how many days X it will take for 24 men to complete the same work. The efficiency of 24 men is:
Efficiency of 24 men=24M
Using the total work calculated:
Total Work=Efficiency of 24 men×Time taken by 24 men
Thus:
576M=24M×X
Step 7: Solve for X
Now, we can solve for X:
X=576M24M=57624=24
Conclusion
Thus, 24 men will take 24 days to complete the same work.
We know that 16 children and 24 men complete a certain work in 18 days.
It is given that each child takes twice the time taken by a man to finish the work. Therefore, if we denote the time taken by a man to complete the work as T, then the time taken by a child will be 2T.
Since work is inversely proportional to time, the efficiency ratio of children to men can be established as follows:
- If one man's efficiency is M, then one child's efficiency will be M2 because a child takes twice as long.
Efficiency of 1 child=M2,Efficiency of 1 man=M
This gives us the ratio:
Efficiency of 1 childEfficiency of 1 man=12
Now, we can calculate the total efficiency of 16 children and 24 men:
- Total efficiency of 16 children = 16×M2=8M
- Total efficiency of 24 men = 24×M=24M
Total efficiency=8M+24M=32M
The total work done can be calculated using the formula:
Total Work=Total Efficiency×Time
Substituting the values we have:
Total Work=32M×18=576M
Now, we need to find out how many days X it will take for 24 men to complete the same work. The efficiency of 24 men is:
Efficiency of 24 men=24M
Using the total work calculated:
Total Work=Efficiency of 24 men×Time taken by 24 men
Thus:
576M=24M×X
Now, we can solve for X:
X=576M24M=57624=24
Thus, 24 men will take 24 days to complete the same work.
Topper's Solved these Questions
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
Similar Questions
Knowledge Check
6 children and 2 men complete a certain piece of work in 6 days. Each child takes twice the time taken by a man to finish the work In how many days will 5 men finish the same work?
A6B8C9D158 children and 12 men complete a certain piece of work in 9 days. Each child takes twice the time taken by a man to finish the work. In how many days will 12 men finish the same work?
A8B15C9D126 children and 2 men complete a certain piece of work in 6 days. Each child takes twice the time taken by a man to finish the work. In how many days will 5 men finish the same work?
A6B8C9D15
If 4 men or 7 women can do a work in 60 days, then in how many days will 8 men and 7 women finish the same work?
View Solution30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?
View SolutionIf 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?
View Solution8 children and 12 men complete a certain piece of work in 9 days. Each child takes twice the time taken by a man to finish the work. In how many days will 12 men finish the same work?
View SolutionSixteen men can finish a work in 8 days. Eight men and nine women working together can finish the same work in 10 days. In how many days will twenty women finish the same work?
View Solution