450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?
50
60
54
45
The correct Answer is:A
To solve the problem step by step, we will first define the variables and then set up the equations based on the information given in the question.
Step 1: Define Variables
Let:
- N = initial number of men
- D = initial number of days required to complete the work
Step 2: Set Up the Equation for Work
The total work can be expressed in terms of man-days:
Total Work=N×D=450 man-days
From this, we can express D in terms of N:
D=450N
Step 3: Set Up the New Scenario
When the number of men is increased by 27, the new number of men is N+27 and the new number of days required is D−15. The total work remains the same:
(N+27)(D−15)=450
Step 4: Substitute D in the New Equation
Substituting D=450N into the new equation:
(N+27)(450N−15)=450
Step 5: Simplify the Equation
Expanding the equation:
(N+27)(450−15NN)=450
Multiplying both sides by N:
(N+27)(450−15N)=450N
Expanding this gives:
450N+12150−15N2−405N=450N
This simplifies to:
12150−15N2−405N=0
Step 6: Rearranging the Equation
Rearranging gives us:
15N2+405N−12150=0
Dividing the entire equation by 15:
N2+27N−810=0
Step 7: Solve the Quadratic Equation
Using the quadratic formula N=−b±√b2−4ac2a:
Here, a=1,b=27,c=−810:
N=−27±√272−4×1×(−810)2×1
Calculating the discriminant:
272+3240=729+3240=3969
Taking the square root:
√3969=63
Now substituting back:
N=−27±632
Calculating the two possible values for N:
1. N=362=18
2. N=−902=−45 (not valid since number of men cannot be negative)
Thus, N=18.
Step 8: Find Initial Days D
Now substituting N back to find D:
D=450N=45018=25 days
Step 9: Calculate Days for Three Times the Work
The total work for three times the original work is:
3×450=1350 man-days
Now, we need to find the number of days required by 27 men to complete this work:
Days=135027=50 days
Final Answer
The number of days required to complete three times the work by 27 men is 50 days.
---
Let:
- N = initial number of men
- D = initial number of days required to complete the work
The total work can be expressed in terms of man-days:
Total Work=N×D=450 man-days
From this, we can express D in terms of N:
D=450N
When the number of men is increased by 27, the new number of men is N+27 and the new number of days required is D−15. The total work remains the same:
(N+27)(D−15)=450
Substituting D=450N into the new equation:
(N+27)(450N−15)=450
Expanding the equation:
(N+27)(450−15NN)=450
Multiplying both sides by N:
(N+27)(450−15N)=450N
Expanding this gives:
450N+12150−15N2−405N=450N
This simplifies to:
12150−15N2−405N=0
Rearranging gives us:
15N2+405N−12150=0
Dividing the entire equation by 15:
N2+27N−810=0
Using the quadratic formula N=−b±√b2−4ac2a:
Here, a=1,b=27,c=−810:
N=−27±√272−4×1×(−810)2×1
Calculating the discriminant:
272+3240=729+3240=3969
Taking the square root:
√3969=63
Now substituting back:
N=−27±632
Calculating the two possible values for N:
1. N=362=18
2. N=−902=−45 (not valid since number of men cannot be negative)
Now substituting N back to find D:
D=450N=45018=25 days
The total work for three times the original work is:
3×450=1350 man-days
Now, we need to find the number of days required by 27 men to complete this work:
Days=135027=50 days
The number of days required to complete three times the work by 27 men is 50 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A32 menB30 menC35 menD36 men - Question 2 - Select One
If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
A21B20C24D22 - Question 3 - Select One
10 men can make a wall in 8 days. How many men required to complete the same work in half day
A80B100C120D160
Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View SolutionTwelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View SolutionHad been one men less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?
View Solution24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :
View SolutionTwo men and 7 children complete a certain piece of work in 4 days while 4 men and 4 children complete the same work in only 3 days. The number of days required by 1 man to complete the work is
View Solution