450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?

A

50

B

60

C

54

D

45

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first define the variables and then set up the equations based on the information given in the question.

Step 1: Define Variables
Let:
- N = initial number of men
- D = initial number of days required to complete the work

Step 2: Set Up the Equation for Work
The total work can be expressed in terms of man-days:
Total Work=N×D=450 man-days
From this, we can express D in terms of N:
D=450N

Step 3: Set Up the New Scenario
When the number of men is increased by 27, the new number of men is N+27 and the new number of days required is D15. The total work remains the same:
(N+27)(D15)=450

Step 4: Substitute D in the New Equation
Substituting D=450N into the new equation:
(N+27)(450N15)=450

Step 5: Simplify the Equation
Expanding the equation:
(N+27)(45015NN)=450
Multiplying both sides by N:
(N+27)(45015N)=450N
Expanding this gives:
450N+1215015N2405N=450N
This simplifies to:
1215015N2405N=0

Step 6: Rearranging the Equation
Rearranging gives us:
15N2+405N12150=0
Dividing the entire equation by 15:
N2+27N810=0

Step 7: Solve the Quadratic Equation
Using the quadratic formula N=b±b24ac2a:
Here, a=1,b=27,c=810:
N=27±2724×1×(810)2×1
Calculating the discriminant:
272+3240=729+3240=3969
Taking the square root:
3969=63
Now substituting back:
N=27±632
Calculating the two possible values for N:
1. N=362=18
2. N=902=45 (not valid since number of men cannot be negative)

Thus, N=18.

Step 8: Find Initial Days D
Now substituting N back to find D:
D=450N=45018=25 days

Step 9: Calculate Days for Three Times the Work
The total work for three times the original work is:
3×450=1350 man-days
Now, we need to find the number of days required by 27 men to complete this work:
Days=135027=50 days

Final Answer
The number of days required to complete three times the work by 27 men is 50 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A32 men
    B30 men
    C35 men
    D36 men
  • Question 2 - Select One

    If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?

    A21
    B20
    C24
    D22
  • Question 3 - Select One

    10 men can make a wall in 8 days. How many men required to complete the same work in half day

    A80
    B100
    C120
    D160