30 girls can finish a work in 40 days. After how many days should 10 girls leave the work so that it may be finished in 46 days, if all the 30 girls started the work?
18 days
28 days
22 days
30 days
The correct Answer is:B
To solve the problem, we need to determine after how many days 10 girls should leave the work so that the remaining work can be completed in a total of 46 days.
1. Calculate the Total Work:
The total work can be calculated in terms of "girl-days". If 30 girls can finish the work in 40 days, the total work is:
Total Work=30 girls×40 days=1200 girl-days
Hint: Remember that "girl-days" is a way to express the total amount of work done by a certain number of girls over a certain number of days.
2. Determine the Work Done in 46 Days:
Since we want the work to be completed in 46 days, we need to find out how much work can be done by 30 girls in the initial days and then by 20 girls after 10 girls leave.
3. Let x be the number of days all 30 girls work:
In the first x days, the work done by 30 girls is:
Work done=30 girls×x days=30x girl-days
4. Calculate Remaining Days:
After x days, the remaining days to complete the work will be:
Remaining Days=46−x
5. Work Done by Remaining Girls:
After x days, 10 girls leave, so 20 girls will work for the remaining days. The work done by 20 girls in the remaining days is:
Work done=20 girls×(46−x) days=20(46−x) girl-days
6. Set Up the Equation:
The total work done by both phases must equal the total work:
30x+20(46−x)=1200
7. Simplify the Equation:
Expanding the equation gives:
30x+920−20x=1200
10x+920=1200
8. Solve for x:
Subtract 920 from both sides:
10x=280
Divide by 10:
x=28
9. Conclusion:
Therefore, the 10 girls should leave after 28 days.
Final Answer:
10 girls should leave the work after 28 days.
The total work can be calculated in terms of "girl-days". If 30 girls can finish the work in 40 days, the total work is:
Total Work=30 girls×40 days=1200 girl-days
Since we want the work to be completed in 46 days, we need to find out how much work can be done by 30 girls in the initial days and then by 20 girls after 10 girls leave.
In the first x days, the work done by 30 girls is:
Work done=30 girls×x days=30x girl-days
After x days, the remaining days to complete the work will be:
Remaining Days=46−x
After x days, 10 girls leave, so 20 girls will work for the remaining days. The work done by 20 girls in the remaining days is:
Work done=20 girls×(46−x) days=20(46−x) girl-days
The total work done by both phases must equal the total work:
30x+20(46−x)=1200
Expanding the equation gives:
30x+920−20x=1200
10x+920=1200
Subtract 920 from both sides:
10x=280
Divide by 10:
x=28
Therefore, the 10 girls should leave after 28 days.
10 girls should leave the work after 28 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days if all the 30 workers started the work.
A12B10C6Dnone of these30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days :
A12B10C6Dnone of these15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is:
A10B20C30D35
30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?
View SolutionWorking 8 hours a day, Ashu can copy a book in 18 days. How many hours a day should he work so as to finish the work in 12 days?
View SolutionWorking 8 hours a day, Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days ?
View SolutionWorking 9 hours a day, Manish can read a book in 16 days. How many hours a day should he work so as to finish the same work in 24 days?
View SolutionWorking 9 hours a day, Manish can read a book in 16 days. How many hours a day should he work so as to finish the same work in 24 days?
View Solution