30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days :

A

12

B

10

C

6

D

none of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to determine how many days 9 workers can work before leaving, such that the total work is completed in 26 days.

1. Calculate Total Work in Worker-Days:
- If 30 workers can finish the work in 20 days, the total work can be calculated as:
Total Work=Number of Workers×Number of Days=30×20=600 worker-days

Hint: Remember that total work is the product of the number of workers and the time they work.

2. Determine the Work Done by 30 Workers in 'x' Days:
- Let 'x' be the number of days that all 30 workers work before 9 workers leave. The work done in 'x' days is:
Work Done=30×x

Hint: Use the same formula for work done as in step 1, but adjust the number of days.

3. Calculate Remaining Days:
- After 'x' days, there are 26x days left to complete the work. During these remaining days, only 21 workers (30 - 9) will be working. The work done in these remaining days is:
Work Done=21×(26x)

Hint: Remember to subtract the days already worked from the total days to find the remaining days.

4. Set Up the Equation:
- The total work done must equal the total work required:
30x+21(26x)=600

Hint: Combine the work done by both groups of workers into one equation.

5. Simplify the Equation:
- Expanding the equation:
30x+54621x=600
- Combine like terms:
9x+546=600

Hint: Make sure to combine all terms carefully to isolate 'x'.

6. Solve for 'x':
- Subtract 546 from both sides:
9x=600546
9x=54
- Divide by 9:
x=6

Hint: When solving for 'x', remember to perform the same operation on both sides of the equation.

7. Conclusion:
- Therefore, 9 workers should leave the job after 6 days.

Final Answer:
9 workers should leave the job after 6 days so that the work is completed in a total of 26 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 30 girls can finish a work in 40 days. After how many days should 10 girls leave the work so that it may be finished in 46 days, if all the 30 girls started the work?

    A18 days
    B28 days
    C22 days
    D30 days
  • 30 girls can finish a work in 40 days. After how many days should 10 girls leave the work so that it may be finished in 46 days, if all the 30 girls started the work?

    A18 days
    B28 days
    C22 days
    D30 days
  • 100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?

    A100
    B60
    C80
    D40