30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days :
12
10
6
none of these
The correct Answer is:C
To solve the problem, we need to determine how many days 9 workers can work before leaving, such that the total work is completed in 26 days.
1. Calculate Total Work in Worker-Days:
- If 30 workers can finish the work in 20 days, the total work can be calculated as:
Total Work=Number of Workers×Number of Days=30×20=600 worker-days
Hint: Remember that total work is the product of the number of workers and the time they work.
2. Determine the Work Done by 30 Workers in 'x' Days:
- Let 'x' be the number of days that all 30 workers work before 9 workers leave. The work done in 'x' days is:
Work Done=30×x
Hint: Use the same formula for work done as in step 1, but adjust the number of days.
3. Calculate Remaining Days:
- After 'x' days, there are 26−x days left to complete the work. During these remaining days, only 21 workers (30 - 9) will be working. The work done in these remaining days is:
Work Done=21×(26−x)
Hint: Remember to subtract the days already worked from the total days to find the remaining days.
4. Set Up the Equation:
- The total work done must equal the total work required:
30x+21(26−x)=600
Hint: Combine the work done by both groups of workers into one equation.
5. Simplify the Equation:
- Expanding the equation:
30x+546−21x=600
- Combine like terms:
9x+546=600
Hint: Make sure to combine all terms carefully to isolate 'x'.
6. Solve for 'x':
- Subtract 546 from both sides:
9x=600−546
9x=54
- Divide by 9:
x=6
Hint: When solving for 'x', remember to perform the same operation on both sides of the equation.
7. Conclusion:
- Therefore, 9 workers should leave the job after 6 days.
Final Answer:
9 workers should leave the job after 6 days so that the work is completed in a total of 26 days.
- If 30 workers can finish the work in 20 days, the total work can be calculated as:
Total Work=Number of Workers×Number of Days=30×20=600 worker-days
- Let 'x' be the number of days that all 30 workers work before 9 workers leave. The work done in 'x' days is:
Work Done=30×x
- After 'x' days, there are 26−x days left to complete the work. During these remaining days, only 21 workers (30 - 9) will be working. The work done in these remaining days is:
Work Done=21×(26−x)
- The total work done must equal the total work required:
30x+21(26−x)=600
- Expanding the equation:
30x+546−21x=600
- Combine like terms:
9x+546=600
- Subtract 546 from both sides:
9x=600−546
9x=54
- Divide by 9:
x=6
- Therefore, 9 workers should leave the job after 6 days.
9 workers should leave the job after 6 days so that the work is completed in a total of 26 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)
55 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- THEORY OF EQUATIONSBOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)
20 Videos
- TIME, SPEED AND DISTANCEBOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)
10 Videos
Similar Questions
30 persons can finish a job in20 days. After 6 days how many persons should leave the job, so that work is completedina total of 26 days?
View SolutionA, B and C can finish a piece of work in 20 days, 25 days and 30 days respectively. They started working together. After how many days A should leave the work so that total work will be complete in 12 days?
View Solution
Knowledge Check
30 girls can finish a work in 40 days. After how many days should 10 girls leave the work so that it may be finished in 46 days, if all the 30 girls started the work?
A18 daysB28 daysC22 daysD30 days30 girls can finish a work in 40 days. After how many days should 10 girls leave the work so that it may be finished in 46 days, if all the 30 girls started the work?
A18 daysB28 daysC22 daysD30 days100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
A100B60C80D40
A, B and C can finish a piece of work in 16 days, 20 days and 24 days respectively. They started working together. How many days before B should leave the work so that work must complete in 7 days?
View Solution15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is:
View Solution25 men can complete a job in 30 days. After how many days should the strength of work force be increased by 50 men so that the work will be completed 23rd in of the actual time:
View SolutionWorking 10 hours a day, Aman can complete a piece of work in 18 days. How many hours a day should he work so as to finish the work in 15 days ?
View SolutionWorking 6 hours a day, Raman can complete a piece of work in 24 days. How many hours a day should he work so as to finish the work in 18 days?
View Solution