A, B and C can finish a piece of work in 20 days, 25 days and 30 days respectively. They started working together. After how many days A should leave the work so that total work will be complete in 12 days?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:225 days


To solve the problem step by step, we can follow these calculations:

Step 1: Determine the work done by A, B, and C in one day.
- A can finish the work in 20 days, so A's work per day = 120
- B can finish the work in 25 days, so B's work per day = 125
- C can finish the work in 30 days, so C's work per day = 130

Step 2: Calculate the total work done by A, B, and C together in one day.
To find the total work done by A, B, and C together in one day, we add their efficiencies:
Total work per day=120+125+130

To add these fractions, we first find the least common multiple (LCM) of the denominators (20, 25, and 30).
- LCM of 20, 25, and 30 is 300.

Now, we convert each fraction to have a denominator of 300:
- A's work: 120=15300
- B's work: 125=12300
- C's work: 130=10300

Now, adding these gives:
Total work per day=15+12+10300=37300

Step 3: Calculate the total work done by B and C in 12 days.
We need to find out how much work B and C can do in 12 days:
Work done by B and C in 12 days=(B+C)×12
First, we find the combined work of B and C:
B+C=12300+10300=22300
Now, work done by B and C in 12 days:
Work done by B and C in 12 days=22300×12=264300=4450=2225

Step 4: Calculate the remaining work.
The total work is 1 (or 300 units). Therefore, the remaining work that A needs to complete is:
Remaining work=12225=325

Step 5: Determine how many days A needs to work to finish the remaining work.
A's work per day is 15300=120. To find out how many days A needs to finish the remaining work:
Days A needs to work=Remaining work÷A's work per day=325÷120=325×20=6025=2.4 days

Step 6: Calculate how many days A should leave the work.
Since they are working together for 12 days, if A works for 2.4 days, then:
Days A should leave=122.4=9.6 days

Final Answer:
A should leave the work after approximately 9.6 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and c can complete a piece of work in 10, 20 and 60 days respectively. Working together can complete the same work in how many days?

    A5
    B6
    C10
    D8
  • A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

    Aa)20
    Bb)19
    Cc)30
    Dd)31
  • A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?

    A5
    B6
    C10
    D8