A started a work and left after working for 4 days, then B was called and he finished the work in 18 days. If A left the work after working for 6 days then B would have finished the remaining work in 12 days. In how many days can each of them, working alone finish the whole work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A20 days, B30 day


To solve the problem step by step, let's denote the work done by A in one day as A and the work done by B in one day as B.

Step 1: Set up the equations based on the given information.

1. First Scenario: A works for 4 days and then B finishes the remaining work in 18 days.
- Work done by A in 4 days = 4A
- Work done by B in 18 days = 18B
- Total work = 4A+18B (Equation 1)

2. Second Scenario: A works for 6 days and then B finishes the remaining work in 12 days.
- Work done by A in 6 days = 6A
- Work done by B in 12 days = 12B
- Total work = 6A+12B (Equation 2)

Step 2: Equate the total work from both scenarios.

Since the total work is the same in both scenarios, we can set Equation 1 equal to Equation 2:

4A+18B=6A+12B

Step 3: Simplify the equation.

Rearranging the equation gives:

4A+18B12B=6A
4A+6B=6A
6B=6A4A
6B=2A
AB=3(Equation 3)

Step 4: Substitute A in terms of B.

From Equation 3, we can express A as:

A=3B

Step 5: Substitute A back into one of the total work equations.

Let's substitute A into Equation 1:

4(3B)+18B=Total Work
12B+18B=Total Work
30B=Total Work

Step 6: Find the total work.

Now we know that the total work is 30B.

Step 7: Calculate the number of days each person takes to finish the work alone.

1. For A:
Days taken by A=Total WorkA=30B3B=10 days

2. For B:
Days taken by B=Total WorkB=30BB=30 days

Final Answer:
- A can finish the work alone in 10 days.
- B can finish the work alone in 30 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Arjun started a task and left it after working for 2 days. Then, Bharath was called and he completed the task in 9 days. If Arjun alone had worked for 3 days, Bharath alone would have finished the remaining work in 6 days. In how many days can Arjun alone complete the task?

    A8 days
    B12 days
    C5 days
    D10 days
  • A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?

    A60
    B50
    C40
    D30
  • A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?

    A30
    B27
    C25
    D24