A started a work and left after working for 4 days, then B was called and he finished the work in 18 days. If A left the work after working for 6 days then B would have finished the remaining work in 12 days. In how many days can each of them, working alone finish the whole work?
The correct Answer is:A→20 days, B→30 day
To solve the problem step by step, let's denote the work done by A in one day as A and the work done by B in one day as B.
Step 1: Set up the equations based on the given information.
1. First Scenario: A works for 4 days and then B finishes the remaining work in 18 days.
- Work done by A in 4 days = 4A
- Work done by B in 18 days = 18B
- Total work = 4A+18B (Equation 1)
2. Second Scenario: A works for 6 days and then B finishes the remaining work in 12 days.
- Work done by A in 6 days = 6A
- Work done by B in 12 days = 12B
- Total work = 6A+12B (Equation 2)
Step 2: Equate the total work from both scenarios.
Since the total work is the same in both scenarios, we can set Equation 1 equal to Equation 2:
4A+18B=6A+12B
Step 3: Simplify the equation.
Rearranging the equation gives:
4A+18B−12B=6A
4A+6B=6A
6B=6A−4A
6B=2A
AB=3(Equation 3)
Step 4: Substitute A in terms of B.
From Equation 3, we can express A as:
A=3B
Step 5: Substitute A back into one of the total work equations.
Let's substitute A into Equation 1:
4(3B)+18B=Total Work
12B+18B=Total Work
30B=Total Work
Step 6: Find the total work.
Now we know that the total work is 30B.
Step 7: Calculate the number of days each person takes to finish the work alone.
1. For A:
Days taken by A=Total WorkA=30B3B=10 days
2. For B:
Days taken by B=Total WorkB=30BB=30 days
Final Answer:
- A can finish the work alone in 10 days.
- B can finish the work alone in 30 days.
- Work done by A in 4 days = 4A
- Work done by B in 18 days = 18B
- Total work = 4A+18B (Equation 1)
- Work done by A in 6 days = 6A
- Work done by B in 12 days = 12B
- Total work = 6A+12B (Equation 2)
4A+6B=6A
6B=6A−4A
6B=2A
AB=3(Equation 3)
12B+18B=Total Work
30B=Total Work
Days taken by A=Total WorkA=30B3B=10 days
Days taken by B=Total WorkB=30BB=30 days
- A can finish the work alone in 10 days.
- B can finish the work alone in 30 days.
Topper's Solved these Questions
Similar Questions
A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working , alone, finish the whole work? a. 2.5 days, 7.5 days b. 5 days, 8.5 days c. 5 days, 15 days d. none of these
View SolutionA can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
View Solution
Knowledge Check
Arjun started a task and left it after working for 2 days. Then, Bharath was called and he completed the task in 9 days. If Arjun alone had worked for 3 days, Bharath alone would have finished the remaining work in 6 days. In how many days can Arjun alone complete the task?
A8 daysB12 daysC5 daysD10 daysA and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
A60B50C40D30A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
A30B27C25D24
Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?
View SolutionP can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?
View SolutionA and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?
View SolutionA can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in
View SolutionA can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?
View Solution