(A + B) working together can finish certain piece of work in 8 days and (B + C) can finish it in 12 days. If A works for 4 days and B works for 7 days, rest work is done by C in 9 days. In how many days C will finish the work working alone?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:24 days


To solve the problem step by step, let's denote the efficiencies of A, B, and C as a, b, and c respectively.

Step 1: Calculate the efficiencies of A + B and B + C
Given:
- A + B can finish the work in 8 days.
- B + C can finish the work in 12 days.

The total work can be represented as 1 unit of work. Therefore, we can express the efficiencies as follows:
- Efficiency of A + B:
a+b=18(work done in one day)
- Efficiency of B + C:
b+c=112(work done in one day)

Step 2: Find the total work done by A and B in 4 days and B in 7 days
From the problem, A works for 4 days and B works for 7 days. The work done by A and B can be calculated as:
- Work done by A in 4 days:
4a
- Work done by B in 7 days:
7b

Step 3: Calculate the remaining work done by C
The total work is 1 unit, so the remaining work after A and B have worked is done by C in 9 days:
- Work done by C in 9 days:
9c

Step 4: Set up the equation for total work
Now we can set up the equation for the total work:
4a+7b+9c=1

Step 5: Substitute the values of a + b and b + c
From the previous steps, we have:
1. a+b=18
2. b+c=112

We can express a and c in terms of b:
- From a+b=18:
a=18b
- From b+c=112:
c=112b

Step 6: Substitute a and c into the total work equation
Substituting a and c into the total work equation:
4(18b)+7b+9(112b)=1

Step 7: Simplify the equation
Expanding the equation:
484b+7b+9129b=1
124b+7b+349b=1
Combining like terms:
12+346b=1
Convert 12 to quarters:
24+346b=1
546b=1
Subtract 54 from both sides:
6b=154
6b=4454=14
Dividing both sides by -6:
b=124

Step 8: Find a and c
Now substitute b back to find a and c:
a=18124=324124=224=112
c=112124=224124=124

Step 9: Calculate the time taken by C to finish the work alone
Since c=124, this means C can finish the work in:
Time taken by C=1c=1124=24 days

Final Answer
C will finish the work alone in 24 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?

    A48
    B60
    C24
    D30
  • A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?

    A4 days
    B6 days
    C2 days
    D3 days
  • A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together?

    A4 days
    B2 days
    C3 days
    D6 days