(A + B) working together can finish certain piece of work in 8 days and (B + C) can finish it in 12 days. If A works for 4 days and B works for 7 days, rest work is done by C in 9 days. In how many days C will finish the work working alone?
The correct Answer is:24 days
To solve the problem step by step, let's denote the efficiencies of A, B, and C as a, b, and c respectively.
Step 1: Calculate the efficiencies of A + B and B + C
Given:
- A + B can finish the work in 8 days.
- B + C can finish the work in 12 days.
The total work can be represented as 1 unit of work. Therefore, we can express the efficiencies as follows:
- Efficiency of A + B:
a+b=18(work done in one day)
- Efficiency of B + C:
b+c=112(work done in one day)
Step 2: Find the total work done by A and B in 4 days and B in 7 days
From the problem, A works for 4 days and B works for 7 days. The work done by A and B can be calculated as:
- Work done by A in 4 days:
4a
- Work done by B in 7 days:
7b
Step 3: Calculate the remaining work done by C
The total work is 1 unit, so the remaining work after A and B have worked is done by C in 9 days:
- Work done by C in 9 days:
9c
Step 4: Set up the equation for total work
Now we can set up the equation for the total work:
4a+7b+9c=1
Step 5: Substitute the values of a + b and b + c
From the previous steps, we have:
1. a+b=18
2. b+c=112
We can express a and c in terms of b:
- From a+b=18:
a=18−b
- From b+c=112:
c=112−b
Step 6: Substitute a and c into the total work equation
Substituting a and c into the total work equation:
4(18−b)+7b+9(112−b)=1
Step 7: Simplify the equation
Expanding the equation:
48−4b+7b+912−9b=1
12−4b+7b+34−9b=1
Combining like terms:
12+34−6b=1
Convert 12 to quarters:
24+34−6b=1
54−6b=1
Subtract 54 from both sides:
−6b=1−54
−6b=44−54=−14
Dividing both sides by -6:
b=124
Step 8: Find a and c
Now substitute b back to find a and c:
a=18−124=324−124=224=112
c=112−124=224−124=124
Step 9: Calculate the time taken by C to finish the work alone
Since c=124, this means C can finish the work in:
Time taken by C=1c=1124=24 days
Final Answer
C will finish the work alone in 24 days.
Given:
- A + B can finish the work in 8 days.
- B + C can finish the work in 12 days.
- Efficiency of A + B:
a+b=18(work done in one day)
- Efficiency of B + C:
b+c=112(work done in one day)
From the problem, A works for 4 days and B works for 7 days. The work done by A and B can be calculated as:
- Work done by A in 4 days:
4a
- Work done by B in 7 days:
7b
The total work is 1 unit, so the remaining work after A and B have worked is done by C in 9 days:
- Work done by C in 9 days:
9c
Now we can set up the equation for the total work:
4a+7b+9c=1
From the previous steps, we have:
1. a+b=18
2. b+c=112
- From a+b=18:
a=18−b
- From b+c=112:
c=112−b
Substituting a and c into the total work equation:
4(18−b)+7b+9(112−b)=1
Expanding the equation:
48−4b+7b+912−9b=1
12−4b+7b+34−9b=1
Combining like terms:
12+34−6b=1
Convert 12 to quarters:
24+34−6b=1
54−6b=1
Subtract 54 from both sides:
−6b=1−54
−6b=44−54=−14
Dividing both sides by -6:
b=124
Now substitute b back to find a and c:
a=18−124=324−124=224=112
c=112−124=224−124=124
Since c=124, this means C can finish the work in:
Time taken by C=1c=1124=24 days
C will finish the work alone in 24 days.
Topper's Solved these Questions
Similar Questions
A and C working together can finish certain piece of work in 12 days. A and B can finish same piece of work in 20 days. If A work for 24 days and B for 6 days then rest work done by C in 2 days. Then find in how many days A, B and C can finish same piece of work, working together?
View SolutionA and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?
View Solution
Knowledge Check
A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
A48B60C24D30A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?
A4 daysB6 daysC2 daysD3 daysA can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together?
A4 daysB2 daysC3 daysD6 days
A, B and C working together can finish a piece of work in 32 days. They started working together and worked for 20 days then A left the work. Rest work done by B and C in 20 days. In how many days A working alone will finish the work?
View SolutionA, B and C working together can finish a certain piece of work in 40 days. They work for 25 days and then B left and rest work done by A and C in 20 days. If efficiency of C is half of B's efficiency. Then in how many days A will finish the working alone?
View SolutionA and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
View SolutionA and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in
View Solution