A takes 4 hours more than that of A and B working together to finish certain piece of work. While B takes 9 hours more than that of A and B working together. Then find in how many hours A and B working together can finish the work?
The correct Answer is:6 hours
To solve the problem, we need to find out how many hours A and B together can finish the work. Let's denote the time taken by A and B working together as x hours.
1. Define the Variables:
- Let x be the time taken by A and B working together to complete the work.
- Then, A takes x+4 hours to finish the work alone.
- B takes x+9 hours to finish the work alone.
2. Calculate the Work Done:
- The work done by A in one hour is 1x+4.
- The work done by B in one hour is 1x+9.
- The work done by A and B together in one hour is 1x.
3. Set Up the Equation:
- According to the work rates, the combined work done by A and B in one hour can be expressed as:
1x=1x+4+1x+9
4. Find a Common Denominator:
- The common denominator for the right side of the equation is (x+4)(x+9).
- Rewrite the equation:
1x=(x+9)+(x+4)(x+4)(x+9)
- Simplifying the numerator:
1x=2x+13(x+4)(x+9)
5. Cross-Multiply:
- Cross-multiplying gives:
(2x+13)x=(x+4)(x+9)
6. Expand Both Sides:
- Left side:
2x2+13x
- Right side:
x2+13x+36
7. Set Up the Quadratic Equation:
- Now, equate both sides:
2x2+13x=x2+13x+36
- Simplifying gives:
2x2−x2+13x−13x−36=0
x2−36=0
8. Solve the Quadratic Equation:
- Factoring gives:
(x−6)(x+6)=0
- Thus, x=6 or x=−6 (we discard the negative solution since time cannot be negative).
9. Conclusion:
- Therefore, A and B working together can finish the work in 6 hours.
- Let x be the time taken by A and B working together to complete the work.
- Then, A takes x+4 hours to finish the work alone.
- B takes x+9 hours to finish the work alone.
- The work done by A in one hour is 1x+4.
- The work done by B in one hour is 1x+9.
- The work done by A and B together in one hour is 1x.
- According to the work rates, the combined work done by A and B in one hour can be expressed as:
1x=1x+4+1x+9
- The common denominator for the right side of the equation is (x+4)(x+9).
- Rewrite the equation:
1x=(x+9)+(x+4)(x+4)(x+9)
- Simplifying the numerator:
1x=2x+13(x+4)(x+9)
- Cross-multiplying gives:
(2x+13)x=(x+4)(x+9)
- Left side:
2x2+13x
- Right side:
x2+13x+36
- Now, equate both sides:
2x2+13x=x2+13x+36
- Simplifying gives:
2x2−x2+13x−13x−36=0
x2−36=0
- Factoring gives:
(x−6)(x+6)=0
- Thus, x=6 or x=−6 (we discard the negative solution since time cannot be negative).
- Therefore, A and B working together can finish the work in 6 hours.
Topper's Solved these Questions
Similar Questions
A takes 4 days more to finish certain piece of work than that of B. If working together they can finish the work in 889 days. Then in how many days working alone each can finish the work?
View SolutionA can do a piece of work in 24 hours while B alone can do it in 16 hours. If A, B and C working together can finish in 8 hours, in how many hours will C alone do the work?
View Solution
Knowledge Check
A can do a piece of work in 8 hours while B aline can do it in 12 hours. Both A and B working together can finish the work in time ?
A10 hoursB4 hoursC245 hoursD214 hoursA can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
A9B8C10D6A and B working together can finish a piece of work in 6 days, while A alone can do it in 9 days. How much time will B alone take to finish it?
A18 daysB28 daysC38 daysD08 days
A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionA takes 6 hours more than (A + B + C) together to complete a work. B takes 1 hours more than (A + B + C) together to complete a work. C takes twice as (A + B + C) together to complete a work. In how many days will A and B together complete this work ?
View SolutionEfficiency of A is 34 of B's efficiency and B's efficiency is 80% of C's efficiency. If A takes 120 more days than that of B and C working together to finish a certain piece of work. Then in how many days working together they will finish the work?
View SolutionA, B and C working together can finish certain piece of work in 40 days. If (A + B) work together then take 13 less time than that of C takes alone. If (A + C) work together then they take 14 less time than that of B takes alone. In how many days (B + C) working together will finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View Solution