A, B and C can finish a piece of work in 10 days, 12 days and 15 days respectively. A and B started working together. After working for one day A left the work while C joins. After two days B left the work while A joins. There is holiday on fourth day and then process is repeated till the work in finished. In how many days work would be finished?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:7 days


To solve the problem step by step, we will first determine the work done by A, B, and C individually, then analyze the working pattern described in the question.

Step 1: Determine the work done by A, B, and C in one day.

- A can finish the work in 10 days, so A's work in one day = 110 of the work.
- B can finish the work in 12 days, so B's work in one day = 112 of the work.
- C can finish the work in 15 days, so C's work in one day = 115 of the work.

Step 2: Calculate the combined work of A and B in one day.

The combined work of A and B in one day:
Work of A + Work of B=110+112
To add these fractions, we need a common denominator, which is 60:
110=660,112=560
Thus,
Combined work of A and B=660+560=1160

Step 3: Work done in the first 3 days.

- Day 1: A and B work together: 1160
- Day 2: A leaves, and B and C work together. The work done by B and C in one day:
Work of B + Work of C=112+115
Finding a common denominator (60):
112=560,115=460
Thus,
Combined work of B and C=560+460=960
So, the work done on Day 2 is 960.

- Day 3: A joins again, and A and C work together:
Work of A + Work of C=110+115
Finding a common denominator (30):
110=330,115=230
Thus,
Combined work of A and C=330+230=530=16
So, the work done on Day 3 is 16=1060.

Step 4: Total work done in 3 days.

Adding the work done in the first 3 days:
Total work in 3 days=1160+960+1060=3060=12

Step 5: Work done in 4 days (including the holiday).

Since there is a holiday on the 4th day, the total work done in 4 days remains 12.

Step 6: Repeat the process.

Since 12 of the work is done in 4 days, the remaining work is also 12. The same cycle will repeat, taking another 4 days to complete the remaining work.

Step 7: Total days to finish the work.

The total time taken to finish the work:
Total days=4 days (first half)+4 days (second half)=8 days

Final Answer:
The work would be finished in 8 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can do a piece of work in 10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?

    A2days
    B3days
    C5days
    D4days
  • A, b and C can alone complete a work in 10, 12 and 15 days
    respectively. A and C started the work and after working for
    4 days, A left and B joined. In how many days the total work
    was completed ?

    A659days
    B629days
    C6 days
    D549days
  • A, B and C can do a piece of work individually in 8, 12 and 15
    days, respectively. A and B start working but A quits after
    working for 2 days. After this, C joins B till the completion of
    work. In how many days will the work be completed?

    A588days
    B423days
    C6 days
    D3 days