A, B and C can finish a piece of work in 10 days, 12 days and 15 days respectively. A and B started working together. After working for one day A left the work while C joins. After two days B left the work while A joins. There is holiday on fourth day and then process is repeated till the work in finished. In how many days work would be finished?
The correct Answer is:7 days
To solve the problem step by step, we will first determine the work done by A, B, and C individually, then analyze the working pattern described in the question.
Step 1: Determine the work done by A, B, and C in one day.
- A can finish the work in 10 days, so A's work in one day = 110 of the work.
- B can finish the work in 12 days, so B's work in one day = 112 of the work.
- C can finish the work in 15 days, so C's work in one day = 115 of the work.
Step 2: Calculate the combined work of A and B in one day.
The combined work of A and B in one day:
Work of A + Work of B=110+112
To add these fractions, we need a common denominator, which is 60:
110=660,112=560
Thus,
Combined work of A and B=660+560=1160
Step 3: Work done in the first 3 days.
- Day 1: A and B work together: 1160
- Day 2: A leaves, and B and C work together. The work done by B and C in one day:
Work of B + Work of C=112+115
Finding a common denominator (60):
112=560,115=460
Thus,
Combined work of B and C=560+460=960
So, the work done on Day 2 is 960.
- Day 3: A joins again, and A and C work together:
Work of A + Work of C=110+115
Finding a common denominator (30):
110=330,115=230
Thus,
Combined work of A and C=330+230=530=16
So, the work done on Day 3 is 16=1060.
Step 4: Total work done in 3 days.
Adding the work done in the first 3 days:
Total work in 3 days=1160+960+1060=3060=12
Step 5: Work done in 4 days (including the holiday).
Since there is a holiday on the 4th day, the total work done in 4 days remains 12.
Step 6: Repeat the process.
Since 12 of the work is done in 4 days, the remaining work is also 12. The same cycle will repeat, taking another 4 days to complete the remaining work.
Step 7: Total days to finish the work.
The total time taken to finish the work:
Total days=4 days (first half)+4 days (second half)=8 days
Final Answer:
The work would be finished in 8 days.
- B can finish the work in 12 days, so B's work in one day = 112 of the work.
- C can finish the work in 15 days, so C's work in one day = 115 of the work.
Work of A + Work of B=110+112
To add these fractions, we need a common denominator, which is 60:
110=660,112=560
Thus,
Combined work of A and B=660+560=1160
- Day 2: A leaves, and B and C work together. The work done by B and C in one day:
Work of B + Work of C=112+115
Finding a common denominator (60):
112=560,115=460
Thus,
Combined work of B and C=560+460=960
So, the work done on Day 2 is 960.
Work of A + Work of C=110+115
Finding a common denominator (30):
110=330,115=230
Thus,
Combined work of A and C=330+230=530=16
So, the work done on Day 3 is 16=1060.
Total work in 3 days=1160+960+1060=3060=12
Total days=4 days (first half)+4 days (second half)=8 days
The work would be finished in 8 days.
Topper's Solved these Questions
Similar Questions
A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View SolutionA and B cand o a pieces of work in 10 days and 15 days, respectively. They started the work together but B left after sometime and A finished the work in 5 days. After how many days (from the start) did B leave?
View Solution
Knowledge Check
A, B and C can do a piece of work in 10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?
A2daysB3daysC5daysD4daysA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?A659daysB629daysC6 daysD549daysA, B and C can do a piece of work individually in 8, 12 and 15
days, respectively. A and B start working but A quits after
working for 2 days. After this, C joins B till the completion of
work. In how many days will the work be completed?A588daysB423daysC6 daysD3 days
A, B and C can do a piece of work individually in 8, 12 and 15 days respectively. A and B start working, but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed ?
View SolutionA and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the work
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA , B and C can do a piece of work individually in 8 , 12 and 15 days , respectively . A and B start working but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed?
View Solution