A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
To solve the problem step by step, we will first determine the work rates of A and B, then calculate how much work they completed together before B left, and finally find out how many days B worked before leaving.
Step 1: Determine the work rates of A and B
- A can complete the work in 10 days. Therefore, A's work rate is:
Work rate of A=110 (work per day)
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 (work per day)
Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=110+115
- To add these fractions, we need a common denominator. The least common multiple of 10 and 15 is 30.
110=330,115=230
- Therefore, the combined work rate is:
Combined work rate=330+230=530=16 (work per day)
Step 3: Calculate the total work done by A and B together before B leaves
- Let x be the number of days A and B worked together before B left. In those x days, the work done by both A and B is:
Work done together=Combined work rate×x=16×x
Step 4: Calculate the work done by A alone after B leaves
- After B leaves, A completes the remaining work in 5 days. The work done by A in those 5 days is:
Work done by A in 5 days=Work rate of A×5=110×5=510=12
Step 5: Set up the equation for total work
- The total work is equal to the work done together plus the work done by A alone:
Total work=Work done together+Work done by A alone
1=16x+12
Step 6: Solve for x
- To solve for x, first, convert 12 to a fraction with a denominator of 6:
12=36
- Now substitute this back into the equation:
1=16x+36
- Rearranging gives:
1−36=16x
36=16x
- Multiply both sides by 6:
3=x
Step 7: Conclusion
- Therefore, B left after 3 days.
- A can complete the work in 10 days. Therefore, A's work rate is:
Work rate of A=110 (work per day)
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 (work per day)
- When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=110+115
- To add these fractions, we need a common denominator. The least common multiple of 10 and 15 is 30.
110=330,115=230
- Therefore, the combined work rate is:
Combined work rate=330+230=530=16 (work per day)
- Let x be the number of days A and B worked together before B left. In those x days, the work done by both A and B is:
Work done together=Combined work rate×x=16×x
- After B leaves, A completes the remaining work in 5 days. The work done by A in those 5 days is:
Work done by A in 5 days=Work rate of A×5=110×5=510=12
- The total work is equal to the work done together plus the work done by A alone:
Total work=Work done together+Work done by A alone
1=16x+12
- To solve for x, first, convert 12 to a fraction with a denominator of 6:
12=36
- Now substitute this back into the equation:
1=16x+36
- Rearranging gives:
1−36=16x
36=16x
- Multiply both sides by 6:
3=x
- Therefore, B left after 3 days.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - TEST YOUR CONCEPTS (Very Short Answer Type Questions)
30 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Short Answer Type Questions
15 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A and B cand o a pieces of work in 10 days and 15 days, respectively. They started the work together but B left after sometime and A finished the work in 5 days. After how many days (from the start) did B leave?
View SolutionA and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after
View Solution
Knowledge Check
A and B each working alone can do a work in 15days and 25 days , respectively . They started the work together but B left after some time and A finished the remaining work in 7 days . After how many days from the start did B leave ?
A3B5C7D9A and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?
A5 daysB10 daysC11 daysD6 daysRaja and Baja working alone can do a work in 20 days and 15 days respectively. They stared the work together but Baja left after sometime and Raja finished remaining work in 6 days. Find after how many days from start Baja left the work?
A5 daysB4 daysC6 daysD3 days
A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?
View Solution