P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

A

12

B

18

C

4

D

27

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to find out how much work P, Q, and R can do individually in one day, and then calculate how much work is completed by each of them during their working days.

Step 1: Calculate the total work
Assume the total work is 216 units (this is a common multiple of the days taken by P, Q, and R).

Step 2: Calculate the work done by P in one day
P can complete the work in 18 days, so the work done by P in one day is:
Work done by P in one day=216 units18 days=12 units/day

Step 3: Calculate the work done by P in 3 days
In 3 days, P will complete:
Work done by P in 3 days=12 units/day×3 days=36 units

Step 4: Calculate the remaining work after P's contribution
The remaining work after P has worked for 3 days is:
Remaining work=216 units36 units=180 units

Step 5: Calculate the work done by Q in one day
Q can complete the work in 24 days, so the work done by Q in one day is:
Work done by Q in one day=216 units24 days=9 units/day

Step 6: Calculate the work done by Q in 8 days
In 8 days, Q will complete:
Work done by Q in 8 days=9 units/day×8 days=72 units

Step 7: Calculate the remaining work after Q's contribution
The remaining work after Q has worked for 8 days is:
Remaining work=180 units72 units=108 units

Step 8: Calculate the work done by R in one day
R can complete the work in 36 days, so the work done by R in one day is:
Work done by R in one day=216 units36 days=6 units/day

Step 9: Calculate the time taken by R to complete the remaining work
To find out how many days R takes to complete the remaining 108 units, we use the formula:
Time taken by R=Remaining workWork done by R in one day=108 units6 units/day=18 days

Final Answer
R worked for 18 days to complete the remaining part of the job.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?

    A10
    B12
    C15
    D16
  • A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
    A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?

    A9
    B17(12)
    C12(12)
    D7(12)
  • A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C started the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is :

    A9
    B712
    C1712
    D1212