P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
12
18
4
27
The correct Answer is:B
To solve the problem, we need to find out how much work P, Q, and R can do individually in one day, and then calculate how much work is completed by each of them during their working days.
Step 1: Calculate the total work
Assume the total work is 216 units (this is a common multiple of the days taken by P, Q, and R).
Step 2: Calculate the work done by P in one day
P can complete the work in 18 days, so the work done by P in one day is:
Work done by P in one day=216 units18 days=12 units/day
Step 3: Calculate the work done by P in 3 days
In 3 days, P will complete:
Work done by P in 3 days=12 units/day×3 days=36 units
Step 4: Calculate the remaining work after P's contribution
The remaining work after P has worked for 3 days is:
Remaining work=216 units−36 units=180 units
Step 5: Calculate the work done by Q in one day
Q can complete the work in 24 days, so the work done by Q in one day is:
Work done by Q in one day=216 units24 days=9 units/day
Step 6: Calculate the work done by Q in 8 days
In 8 days, Q will complete:
Work done by Q in 8 days=9 units/day×8 days=72 units
Step 7: Calculate the remaining work after Q's contribution
The remaining work after Q has worked for 8 days is:
Remaining work=180 units−72 units=108 units
Step 8: Calculate the work done by R in one day
R can complete the work in 36 days, so the work done by R in one day is:
Work done by R in one day=216 units36 days=6 units/day
Step 9: Calculate the time taken by R to complete the remaining work
To find out how many days R takes to complete the remaining 108 units, we use the formula:
Time taken by R=Remaining workWork done by R in one day=108 units6 units/day=18 days
Final Answer
R worked for 18 days to complete the remaining part of the job.
---
Assume the total work is 216 units (this is a common multiple of the days taken by P, Q, and R).
P can complete the work in 18 days, so the work done by P in one day is:
Work done by P in one day=216 units18 days=12 units/day
In 3 days, P will complete:
Work done by P in 3 days=12 units/day×3 days=36 units
The remaining work after P has worked for 3 days is:
Remaining work=216 units−36 units=180 units
Q can complete the work in 24 days, so the work done by Q in one day is:
Work done by Q in one day=216 units24 days=9 units/day
In 8 days, Q will complete:
Work done by Q in 8 days=9 units/day×8 days=72 units
The remaining work after Q has worked for 8 days is:
Remaining work=180 units−72 units=108 units
R can complete the work in 36 days, so the work done by R in one day is:
Work done by R in one day=216 units36 days=6 units/day
To find out how many days R takes to complete the remaining 108 units, we use the formula:
Time taken by R=Remaining workWork done by R in one day=108 units6 units/day=18 days
R worked for 18 days to complete the remaining part of the job.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)
20 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
P,Q and R can complete a job in 20 days, 30 and 40 days respectiely. They started working on it. Q and R left afte working for certain number of days and P alone completed the remaing work 7 days. Find the time taken to complete the job (in days)
View SolutionP,Q and R can complete a work in 12,24 and 6 days respectively. The work will be completed in __ days if all of them are working together.
View Solution
Knowledge Check
A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
A10B12C15D16A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?A9B17(12)C12(12)D7(12)A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C started the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is :
A9B712C1712D1212
A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is:
A, B और C अकेले-अकेले किसी कार्य को क्रमशः 24, 15 और 12 दिनों में पूरा कर सकते हैं |B और C ने कार्य करना शुरू किया तथा 3 दिनों तक कार्य करके छोड़ दिया| शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?
View SolutionA, B and C can individually complete a piece of work in 24 days, 15 days and 12 days. respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is :
View SolutionP,Q and R can complete a job in 6 days, 9 days and 12 days, respectively. They worked together and completed it. They earned a total of Rs. 2600. Find P's share ( in Rs.)
View SolutionP, Q and R alone can complete a work in 12. 15 and 20 days respectively. In how many days will they together complete the same work?
View SolutionP, Q and R alone can complete a work in 12. 15 and 20 days respectively. In how many days will they together complete the same work?
View Solution