A and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after

A

6 days

B

9 days

C

12 days

D

5 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the total work
To find the total work, we need to calculate the least common multiple (LCM) of the number of days A and B take to complete the work individually.

- A can complete the work in 45 days.
- B can complete the work in 40 days.

LCM of 45 and 40:
- Prime factorization of 45: 32×51
- Prime factorization of 40: 23×51

The LCM is found by taking the highest power of each prime:
- LCM = 23×32×51=8×9×5=360

Total work = 360 units.

Step 2: Calculate the work done by A and B in one day
Now, we calculate how much work A and B can do in one day.

- Work done by A in one day = 36045=8 units
- Work done by B in one day = 36040=9 units

Step 3: Calculate the total work done by B in 23 days
Since B worked alone for 23 days after A left, we calculate the work done by B in that time.

- Work done by B in 23 days = 9×23=207 units

Step 4: Calculate the remaining work after B's contribution
Now, we find out how much work was completed before B worked alone.

- Total work = 360 units
- Work done by B = 207 units
- Remaining work = 360207=153 units

Step 5: Calculate the combined work done by A and B together
Next, we calculate how much work A and B can do together in one day.

- Combined work done by A and B in one day = 8+9=17 units

Step 6: Determine how many days A and B worked together
Now, we find out how many days A and B worked together to complete the remaining work of 153 units.

- Days worked together = 15317=9 days

Conclusion
A and B worked together for 9 days before A left the work.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?

    A5 days
    B10 days
    C11 days
    D6 days
  • A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?

    A1425 days
    B9days
    C8days
    D759 days
  • A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

    A2 days
    B3 days
    C1 day
    DNone of these