Some staff promised to do a job in 18 days, but 6 of them went on leave. So the remaining men took 20 days to complete the job. How many men were there originally?
55
62
56
60
The correct Answer is:D
To solve the problem step by step, let's break it down:
Step 1: Define the variables
Let X be the original number of staff members.
Step 2: Set up the equations
The staff promised to complete the job in 18 days. Therefore, the total work done can be expressed as:
Work=Number of persons×Number of days=X×18
When 6 staff members went on leave, the remaining staff is X−6. They completed the same job in 20 days:
Work=(X−6)×20
Step 3: Equate the two expressions for work
Since the total work done is the same in both cases, we can set the two equations equal to each other:
X×18=(X−6)×20
Step 4: Expand and simplify the equation
Expanding the right side:
18X=20X−120
Step 5: Rearrange the equation
Now, move all terms involving X to one side:
18X−20X=−120
−2X=−120
Step 6: Solve for X
Dividing both sides by -2:
X=1202=60
Conclusion
Thus, the original number of staff members was 60.
---
Let X be the original number of staff members.
The staff promised to complete the job in 18 days. Therefore, the total work done can be expressed as:
Work=Number of persons×Number of days=X×18
Work=(X−6)×20
Since the total work done is the same in both cases, we can set the two equations equal to each other:
X×18=(X−6)×20
Expanding the right side:
18X=20X−120
Now, move all terms involving X to one side:
18X−20X=−120
−2X=−120
Dividing both sides by -2:
X=1202=60
Thus, the original number of staff members was 60.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-IV32videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF25videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
Knowledge Check
- Question 1 - Select One
Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
A24B20C16D18 - Question 2 - Select One
Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?
A10B15C12D14 - Question 3 - Select One
Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?
A10B21C15D18
If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionA group of men deaded to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?
View SolutionA group of men deaded to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?
View SolutionA group of men decided to do a job in 8 days. But since 10 men dropped out every day, the job got completed at the end of the 12th day. How many men were there at the beginning?
View Solution