Some staff promised to do a job in 18 days, but 6 of them went on leave. So the remaining men took 20 days to complete the job. How many men were there originally?

A

55

B

62

C

56

D

60

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break it down:

Step 1: Define the variables
Let X be the original number of staff members.

Step 2: Set up the equations
The staff promised to complete the job in 18 days. Therefore, the total work done can be expressed as:
Work=Number of persons×Number of days=X×18

When 6 staff members went on leave, the remaining staff is X6. They completed the same job in 20 days:
Work=(X6)×20

Step 3: Equate the two expressions for work
Since the total work done is the same in both cases, we can set the two equations equal to each other:
X×18=(X6)×20

Step 4: Expand and simplify the equation
Expanding the right side:
18X=20X120

Step 5: Rearrange the equation
Now, move all terms involving X to one side:
18X20X=120
2X=120

Step 6: Solve for X
Dividing both sides by -2:
X=1202=60

Conclusion
Thus, the original number of staff members was 60.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

    A24
    B20
    C16
    D18
  • Question 2 - Select One

    Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?

    A10
    B15
    C12
    D14
  • Question 3 - Select One

    Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?

    A10
    B21
    C15
    D18