A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
13
12
14
11
The correct Answer is:D
To solve the problem step by step, we will calculate the total work done by A, B, and C, and then determine how long it took to complete the work given that C left 4 days before the work was finished.
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 24 days, so A's work in one day = 1/24 of the work.
- B can complete the work in 30 days, so B's work in one day = 1/30 of the work.
- C can complete the work in 40 days, so C's work in one day = 1/40 of the work.
Step 2: Find the total work done by A, B, and C in one day.
To find the total work done by A, B, and C together in one day, we need to add their individual work rates:
Total work in one day=124+130+140
Step 3: Calculate the least common multiple (LCM) of the denominators.
The LCM of 24, 30, and 40 is 120. We will convert each fraction to have a common denominator of 120:
- A's work: 124=5120
- B's work: 130=4120
- C's work: 140=3120
Now, add these fractions:
Total work in one day=5120+4120+3120=12120=110
Step 4: Determine the work done in the last 4 days.
Since C left 4 days before the work was completed, only A and B worked during those last 4 days.
- A's work in one day = 5120
- B's work in one day = 4120
Together, A and B's work in one day:
A and B's work in one day=5120+4120=9120=340
In 4 days, A and B will complete:
Work done in 4 days=4×340=1240=310
Step 5: Calculate the total work and remaining work.
The total work is 1 (the whole work). If A and B completed 310 of the work in the last 4 days, then the remaining work before those 4 days was:
Remaining work=1−310=710
Step 6: Calculate the time taken to complete the remaining work.
To find out how many days it took A, B, and C to complete the remaining 710 of the work, we use their combined work rate:
Work rate of A, B, C=110 (from Step 3)
Let x be the number of days they worked together:
110×x=710
Solving for x:
x=7 days
Step 7: Calculate the total time taken to complete the work.
The total time taken to complete the work is the time they worked together plus the last 4 days:
Total time=7+4=11 days
Final Answer:
The work was completed in 11 days.
---
- A can complete the work in 24 days, so A's work in one day = 1/24 of the work.
- B can complete the work in 30 days, so B's work in one day = 1/30 of the work.
- C can complete the work in 40 days, so C's work in one day = 1/40 of the work.
To find the total work done by A, B, and C together in one day, we need to add their individual work rates:
Total work in one day=124+130+140
The LCM of 24, 30, and 40 is 120. We will convert each fraction to have a common denominator of 120:
- A's work: 124=5120
- B's work: 130=4120
- C's work: 140=3120
Total work in one day=5120+4120+3120=12120=110
Since C left 4 days before the work was completed, only A and B worked during those last 4 days.
- A's work in one day = 5120
- B's work in one day = 4120
A and B's work in one day=5120+4120=9120=340
Work done in 4 days=4×340=1240=310
The total work is 1 (the whole work). If A and B completed 310 of the work in the last 4 days, then the remaining work before those 4 days was:
Remaining work=1−310=710
To find out how many days it took A, B, and C to complete the remaining 710 of the work, we use their combined work rate:
Work rate of A, B, C=110 (from Step 3)
Let x be the number of days they worked together:
110×x=710
Solving for x:
x=7 days
The total time taken to complete the work is the time they worked together plus the last 4 days:
Total time=7+4=11 days
The work was completed in 11 days.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-IV32videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF25videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View Solution
Knowledge Check
- Question 1 - Select One
A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
A13B12C14D11 - Question 2 - Select One
A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?
A7B10C12D9 - Question 3 - Select One
X, Y and Z can do a piece of work in 30, 40and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?
A660/47B640/47C680/47D665/47
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View SolutionP can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?
View Solution