A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?

A

13

B

12

C

14

D

11

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will calculate the total work done by A, B, and C, and then determine how long it took to complete the work given that C left 4 days before the work was finished.

Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 24 days, so A's work in one day = 1/24 of the work.
- B can complete the work in 30 days, so B's work in one day = 1/30 of the work.
- C can complete the work in 40 days, so C's work in one day = 1/40 of the work.

Step 2: Find the total work done by A, B, and C in one day.
To find the total work done by A, B, and C together in one day, we need to add their individual work rates:
Total work in one day=124+130+140

Step 3: Calculate the least common multiple (LCM) of the denominators.
The LCM of 24, 30, and 40 is 120. We will convert each fraction to have a common denominator of 120:
- A's work: 124=5120
- B's work: 130=4120
- C's work: 140=3120

Now, add these fractions:
Total work in one day=5120+4120+3120=12120=110

Step 4: Determine the work done in the last 4 days.
Since C left 4 days before the work was completed, only A and B worked during those last 4 days.
- A's work in one day = 5120
- B's work in one day = 4120

Together, A and B's work in one day:
A and B's work in one day=5120+4120=9120=340

In 4 days, A and B will complete:
Work done in 4 days=4×340=1240=310

Step 5: Calculate the total work and remaining work.
The total work is 1 (the whole work). If A and B completed 310 of the work in the last 4 days, then the remaining work before those 4 days was:
Remaining work=1310=710

Step 6: Calculate the time taken to complete the remaining work.
To find out how many days it took A, B, and C to complete the remaining 710 of the work, we use their combined work rate:
Work rate of A, B, C=110 (from Step 3)
Let x be the number of days they worked together:
110×x=710
Solving for x:
x=7 days

Step 7: Calculate the total time taken to complete the work.
The total time taken to complete the work is the time they worked together plus the last 4 days:
Total time=7+4=11 days

Final Answer:
The work was completed in 11 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?

    A13
    B12
    C14
    D11
  • Question 2 - Select One

    A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?

    A7
    B10
    C12
    D9
  • Question 3 - Select One

    X, Y and Z can do a piece of work in 30, 40and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?

    A660/47
    B640/47
    C680/47
    D665/47