P can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?

A

8

B

10

C

9

D

11

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we can follow these calculations:

Step 1: Determine the work done by P and Q in one day
- P can complete the work in 15 days, so the work done by P in one day is:
Work done by P in one day=115 of the work
- Q can complete the work in 24 days, so the work done by Q in one day is:
Work done by Q in one day=124 of the work

Step 2: Find the combined work done by P and Q in one day
- To find the combined work done by P and Q in one day, we can add their individual work rates:
Combined work rate=115+124
- To add these fractions, we need a common denominator. The LCM of 15 and 24 is 120. Thus:
115=8120and124=5120
- Therefore,
Combined work rate=8120+5120=13120

Step 3: Calculate the total work done before Q leaves
- Let x be the number of days they worked together before Q leaves. Since Q leaves 2 days before the work is completed, P works alone for 2 days after Q leaves.
- In x days, the total work done by both P and Q is:
Work done together=x×13120
- In the 2 days that P works alone, the work done is:
Work done by P alone=2×115=215

Step 4: Set up the equation for total work
- The total work is equal to 1 (the whole work), so we can set up the equation:
x×13120+215=1

Step 5: Solve for x
- First, convert 215 to a fraction with a denominator of 120:
215=16120
- Now, substitute back into the equation:
x×13120+16120=1
- Multiply through by 120 to eliminate the denominator:
13x+16=120
- Rearranging gives:
13x=12016=104
- Solving for x:
x=10413=8

Step 6: Calculate the total time taken to complete the work
- Since they worked together for 8 days and P worked alone for 2 days:
Total time=8+2=10 days

Final Answer:
The work was completed in 10 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

    A12
    B10
    C9.6
    D9
  • P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed

    A9 days
    B14 days
    C12 days
    D18 days
  • A and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?

    A13 days
    B8 days
    C6 days
    D5 days