P can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?
8
10
9
11
The correct Answer is:B
To solve the problem step by step, we can follow these calculations:
Step 1: Determine the work done by P and Q in one day
- P can complete the work in 15 days, so the work done by P in one day is:
Work done by P in one day=115 of the work
- Q can complete the work in 24 days, so the work done by Q in one day is:
Work done by Q in one day=124 of the work
Step 2: Find the combined work done by P and Q in one day
- To find the combined work done by P and Q in one day, we can add their individual work rates:
Combined work rate=115+124
- To add these fractions, we need a common denominator. The LCM of 15 and 24 is 120. Thus:
115=8120and124=5120
- Therefore,
Combined work rate=8120+5120=13120
Step 3: Calculate the total work done before Q leaves
- Let x be the number of days they worked together before Q leaves. Since Q leaves 2 days before the work is completed, P works alone for 2 days after Q leaves.
- In x days, the total work done by both P and Q is:
Work done together=x×13120
- In the 2 days that P works alone, the work done is:
Work done by P alone=2×115=215
Step 4: Set up the equation for total work
- The total work is equal to 1 (the whole work), so we can set up the equation:
x×13120+215=1
Step 5: Solve for x
- First, convert 215 to a fraction with a denominator of 120:
215=16120
- Now, substitute back into the equation:
x×13120+16120=1
- Multiply through by 120 to eliminate the denominator:
13x+16=120
- Rearranging gives:
13x=120−16=104
- Solving for x:
x=10413=8
Step 6: Calculate the total time taken to complete the work
- Since they worked together for 8 days and P worked alone for 2 days:
Total time=8+2=10 days
Final Answer:
The work was completed in 10 days.
---
- P can complete the work in 15 days, so the work done by P in one day is:
Work done by P in one day=115 of the work
- Q can complete the work in 24 days, so the work done by Q in one day is:
Work done by Q in one day=124 of the work
- To find the combined work done by P and Q in one day, we can add their individual work rates:
Combined work rate=115+124
- To add these fractions, we need a common denominator. The LCM of 15 and 24 is 120. Thus:
115=8120and124=5120
- Therefore,
Combined work rate=8120+5120=13120
- Let x be the number of days they worked together before Q leaves. Since Q leaves 2 days before the work is completed, P works alone for 2 days after Q leaves.
- In x days, the total work done by both P and Q is:
Work done together=x×13120
- In the 2 days that P works alone, the work done is:
Work done by P alone=2×115=215
- The total work is equal to 1 (the whole work), so we can set up the equation:
x×13120+215=1
- First, convert 215 to a fraction with a denominator of 120:
215=16120
- Now, substitute back into the equation:
x×13120+16120=1
- Multiply through by 120 to eliminate the denominator:
13x+16=120
- Rearranging gives:
13x=120−16=104
- Solving for x:
x=10413=8
- Since they worked together for 8 days and P worked alone for 2 days:
Total time=8+2=10 days
The work was completed in 10 days.
Similar Questions
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8
View SolutionA, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
View Solution
Knowledge Check
A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
A12B10C9.6D9P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
A9 daysB14 daysC12 daysD18 daysA and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
A13 daysB8 daysC6 daysD5 days
F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
View Solution