A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A

7310

B

10215

C

10730

D

none of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work done by A, B, and C, and then calculate how long it took to complete the work given the conditions.

Step 1: Determine the work rates of A, B, and C
- A can complete the work in 15 days, so A's work rate is 115 of the work per day.
- B can complete the work in 30 days, so B's work rate is 130 of the work per day.
- C can complete the work in 40 days, so C's work rate is 140 of the work per day.

Step 2: Find the combined work rate of A, B, and C
To find the combined work rate, we need to find a common denominator for their work rates:
- The LCM of 15, 30, and 40 is 120.
- A's work rate in terms of units of work is 12015=8 units per day.
- B's work rate in terms of units of work is 12030=4 units per day.
- C's work rate in terms of units of work is 12040=3 units per day.

Thus, the combined work rate of A, B, and C is:
8+4+3=15 units per day

Step 3: Determine the work done in the last days
Let x be the total number of days taken to complete the work. According to the problem:
- A left 2 days before completion, so A worked for x2 days.
- B left 4 days before completion, so B worked for x4 days.
- C worked for all x days.

Step 4: Calculate the total work done
The total work done can be expressed as:
Work done by A=8(x2)
Work done by B=4(x4)
Work done by C=3x

The total work done is equal to the total work (120 units):
8(x2)+4(x4)+3x=120

Step 5: Simplify the equation
Expanding the equation:
8x16+4x16+3x=120
Combining like terms:
(8x+4x+3x)32=120
15x32=120

Step 6: Solve for x
Adding 32 to both sides:
15x=152
Dividing by 15:
x=1521510.13

Step 7: Determine the total days taken
Since x must be a whole number, we round up to the nearest whole number, which gives us x=11 days.

Final Answer
The total number of days taken to complete the work is 11 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10
  • A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?

    A13
    B12
    C14
    D11
  • A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

    Aa)20
    Bb)19
    Cc)30
    Dd)31