A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
7310
10215
10730
none of these
The correct Answer is:B
To solve the problem step by step, we will first determine the work done by A, B, and C, and then calculate how long it took to complete the work given the conditions.
Step 1: Determine the work rates of A, B, and C
- A can complete the work in 15 days, so A's work rate is 115 of the work per day.
- B can complete the work in 30 days, so B's work rate is 130 of the work per day.
- C can complete the work in 40 days, so C's work rate is 140 of the work per day.
Step 2: Find the combined work rate of A, B, and C
To find the combined work rate, we need to find a common denominator for their work rates:
- The LCM of 15, 30, and 40 is 120.
- A's work rate in terms of units of work is 12015=8 units per day.
- B's work rate in terms of units of work is 12030=4 units per day.
- C's work rate in terms of units of work is 12040=3 units per day.
Thus, the combined work rate of A, B, and C is:
8+4+3=15 units per day
Step 3: Determine the work done in the last days
Let x be the total number of days taken to complete the work. According to the problem:
- A left 2 days before completion, so A worked for x−2 days.
- B left 4 days before completion, so B worked for x−4 days.
- C worked for all x days.
Step 4: Calculate the total work done
The total work done can be expressed as:
Work done by A=8(x−2)
Work done by B=4(x−4)
Work done by C=3x
The total work done is equal to the total work (120 units):
8(x−2)+4(x−4)+3x=120
Step 5: Simplify the equation
Expanding the equation:
8x−16+4x−16+3x=120
Combining like terms:
(8x+4x+3x)−32=120
15x−32=120
Step 6: Solve for x
Adding 32 to both sides:
15x=152
Dividing by 15:
x=15215≈10.13
Step 7: Determine the total days taken
Since x must be a whole number, we round up to the nearest whole number, which gives us x=11 days.
Final Answer
The total number of days taken to complete the work is 11 days.
---
- A can complete the work in 15 days, so A's work rate is 115 of the work per day.
- B can complete the work in 30 days, so B's work rate is 130 of the work per day.
- C can complete the work in 40 days, so C's work rate is 140 of the work per day.
To find the combined work rate, we need to find a common denominator for their work rates:
- The LCM of 15, 30, and 40 is 120.
- A's work rate in terms of units of work is 12015=8 units per day.
- B's work rate in terms of units of work is 12030=4 units per day.
- C's work rate in terms of units of work is 12040=3 units per day.
8+4+3=15 units per day
Let x be the total number of days taken to complete the work. According to the problem:
- A left 2 days before completion, so A worked for x−2 days.
- B left 4 days before completion, so B worked for x−4 days.
- C worked for all x days.
The total work done can be expressed as:
Work done by A=8(x−2)
Work done by B=4(x−4)
Work done by C=3x
8(x−2)+4(x−4)+3x=120
Expanding the equation:
8x−16+4x−16+3x=120
Combining like terms:
(8x+4x+3x)−32=120
15x−32=120
Adding 32 to both sides:
15x=152
Dividing by 15:
x=15215≈10.13
Since x must be a whole number, we round up to the nearest whole number, which gives us x=11 days.
The total number of days taken to complete the work is 11 days.
Topper's Solved these Questions
Similar Questions
A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View Solution
Knowledge Check
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
A13B12C14D11A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
Aa)20Bb)19Cc)30Dd)31
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8
View SolutionA, B and C can do a piece of work in 36, 54 and days respectively. They started the work but A left days before the completion of the work while B 12 days before the completion. The number of days for which C worked is 4 b. 8 c. 12 d. 24
View SolutionA, B and C can complete a work in 8, 16 and 24 days respectively. They start the work together and A works till last moment . If C leaves the work 2 days before and B leaves one day before the completion of the work, in how many days the work will be finished?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View SolutionA, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
View Solution