A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
60
80
20
25
The correct Answer is:C
To solve the problem step by step, we will follow the logic laid out in the video transcript.
Step 1: Understand the total work and initial deployment
The contractor has 40 days to complete the work with 20 men.
Hint: Remember that the total work can be represented as a unit of work that needs to be completed.
Step 2: Calculate the amount of work done in the initial period
The contractor has been working for 32 days (40 days - 8 days remaining). In this time, he has completed half of the work.
Hint: If half of the work is done in 32 days, then the remaining half must be completed in the remaining 8 days.
Step 3: Determine the work left to be done
Since half of the work is completed, there is still 1 unit of work left to be done in the remaining 8 days.
Hint: Think about how much work needs to be done in the remaining time.
Step 4: Calculate the work rate of the initial workforce
The initial workforce of 20 men completed 1 unit of work in 32 days. Therefore, the work rate of 20 men can be calculated as follows:
- Work done by 20 men in 32 days = 1 unit
- Work done by 1 man in 32 days = 1/20 units
- Work done by 1 man in 1 day = 1/(20 * 32) = 1/640 units
Hint: Consider how many units of work one man can do in one day.
Step 5: Determine the work rate needed to complete the remaining work
To complete the remaining 1 unit of work in 8 days, we need to find out how many men (let's call this number X) are required:
- Work required per day = 1 unit / 8 days = 1/8 units per day
Hint: Set up an equation based on the work rate needed to complete the remaining work.
Step 6: Set up the equation for the number of men required
The work done by X men in one day should equal the required work per day:
X×1640=18
To find X, multiply both sides by 640:
X=640×18=80
Hint: Make sure to isolate X to find the total number of men needed.
Step 7: Calculate the additional men required
The contractor initially had 20 men. Now he needs 80 men to complete the work on time. Therefore, the additional number of men required is:
80−20=60
Hint: Subtract the initial number of men from the total number of men needed to find out how many more are required.
Final Answer
The contractor needs 60 more men to complete the work in the stipulated time.
---
The contractor has 40 days to complete the work with 20 men.
The contractor has been working for 32 days (40 days - 8 days remaining). In this time, he has completed half of the work.
Since half of the work is completed, there is still 1 unit of work left to be done in the remaining 8 days.
The initial workforce of 20 men completed 1 unit of work in 32 days. Therefore, the work rate of 20 men can be calculated as follows:
- Work done by 20 men in 32 days = 1 unit
- Work done by 1 man in 32 days = 1/20 units
- Work done by 1 man in 1 day = 1/(20 * 32) = 1/640 units
To complete the remaining 1 unit of work in 8 days, we need to find out how many men (let's call this number X) are required:
- Work required per day = 1 unit / 8 days = 1/8 units per day
The work done by X men in one day should equal the required work per day:
X×1640=18
To find X, multiply both sides by 640:
X=640×18=80
The contractor initially had 20 men. Now he needs 80 men to complete the work on time. Therefore, the additional number of men required is:
80−20=60
The contractor needs 60 more men to complete the work in the stipulated time.
Topper's Solved these Questions
Similar Questions
Knowledge Check
A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
A60B80C20D25A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
A16B15C20D2510 men can make a wall in 8 days. How many men required to complete the same work in half day
A80B100C120D160
20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View SolutionIf 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
View Solution