A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
9 days
15 days
12 days
14 days
The correct Answer is:C
To solve the problem, we will first determine the work rates of A, B, and C, and then calculate how much work is done before C leaves and how much is done after that.
Step 1: Determine the work rates of A, B, and C.
- A can complete the work in 16 days, so A's work rate is 116 of the work per day.
- B can complete the work in 24 days, so B's work rate is 124 of the work per day.
- C can complete the work in 32 days, so C's work rate is 132 of the work per day.
Step 2: Calculate the combined work rate of A, B, and C.
To find the combined work rate, we add their individual work rates:
Combined work rate=116+124+132
To add these fractions, we need a common denominator. The least common multiple (LCM) of 16, 24, and 32 is 96.
Now, we convert each fraction:
- 116=696
- 124=496
- 132=396
Adding these together:
Combined work rate=696+496+396=1396
Step 3: Calculate the work done in the first 4 days.
In the first 4 days, A, B, and C work together:
Work done in 4 days=4×1396=5296=1324
Step 4: Determine the remaining work.
The total work is 1 (whole work), so the remaining work after 4 days is:
Remaining work=1−1324=24−1324=1124
Step 5: Calculate the work rate after C leaves.
After 4 days, C leaves, so only A and B continue to work. Their combined work rate is:
A's work rate+B's work rate=116+124
Using the common denominator of 48:
- 116=348
- 124=248
Thus, the combined work rate of A and B is:
348+248=548
Step 6: Calculate the time taken to finish the remaining work.
Let t be the time taken by A and B to complete the remaining work 1124:
548×t=1124
To solve for t:
t=1124÷548=1124×485=11×25=225=4.4 days
Step 7: Calculate the total time taken to complete the work.
The total time taken is the initial 4 days plus the time taken by A and B to finish the remaining work:
Total time=4+4.4=8.4 days
Final Answer:
The work will be completed in 8.4 days.
- A can complete the work in 16 days, so A's work rate is 116 of the work per day.
- B can complete the work in 24 days, so B's work rate is 124 of the work per day.
- C can complete the work in 32 days, so C's work rate is 132 of the work per day.
To find the combined work rate, we add their individual work rates:
Combined work rate=116+124+132
To add these fractions, we need a common denominator. The least common multiple (LCM) of 16, 24, and 32 is 96.
- 116=696
- 124=496
- 132=396
Combined work rate=696+496+396=1396
In the first 4 days, A, B, and C work together:
Work done in 4 days=4×1396=5296=1324
The total work is 1 (whole work), so the remaining work after 4 days is:
Remaining work=1−1324=24−1324=1124
After 4 days, C leaves, so only A and B continue to work. Their combined work rate is:
A's work rate+B's work rate=116+124
Using the common denominator of 48:
- 116=348
- 124=248
348+248=548
Let t be the time taken by A and B to complete the remaining work 1124:
548×t=1124
To solve for t:
t=1124÷548=1124×485=11×25=225=4.4 days
The total time taken is the initial 4 days plus the time taken by A and B to finish the remaining work:
Total time=4+4.4=8.4 days
The work will be completed in 8.4 days.
Similar Questions
A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of the work. In how many days will the work be completed ? 15 days b. 22 days c. 25 days d. 35 days
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View Solution
Knowledge Check
A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?
A20 daysB18 daysC16 daysD15 daysA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of these
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8
View SolutionA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?
View Solution