A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
The correct Answer is:20
To solve the problem step by step, we will first determine the work done by A, B, and C, and then set up an equation based on the information given in the question.
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 20 days, so A's work in one day = 1/20 of the work.
- B can complete the work in 45 days, so B's work in one day = 1/45 of the work.
- C can complete the work in 120 days, so C's work in one day = 1/120 of the work.
Step 2: Find the Least Common Multiple (LCM) of the days.
The LCM of 20, 45, and 120 is 360. This means the total work can be considered as 360 units.
Step 3: Calculate the efficiency (work done in one day) of A, B, and C.
- A's efficiency = 360 / 20 = 18 units/day.
- B's efficiency = 360 / 45 = 8 units/day.
- C's efficiency = 360 / 120 = 3 units/day.
Step 4: Set up the equation based on the work done.
Let X be the total number of days taken to complete the work.
- A worked for X−10 days (since A left 10 days before completion).
- B worked for X−5 days (since B left 5 days before completion).
- C worked for X days.
Step 5: Write the equation for the total work done.
The total work done by A, B, and C can be expressed as:
18(X−10)+8(X−5)+3X=360
Step 6: Expand and simplify the equation.
Expanding the equation:
18X−180+8X−40+3X=360
Combine like terms:
(18X+8X+3X)−220=360
29X−220=360
Step 7: Solve for X.
Add 220 to both sides:
29X=580
Now, divide by 29:
X=58029
X=20
Conclusion:
The total work is completed in 20 days.
- A can complete the work in 20 days, so A's work in one day = 1/20 of the work.
- B can complete the work in 45 days, so B's work in one day = 1/45 of the work.
- C can complete the work in 120 days, so C's work in one day = 1/120 of the work.
The LCM of 20, 45, and 120 is 360. This means the total work can be considered as 360 units.
- A's efficiency = 360 / 20 = 18 units/day.
- B's efficiency = 360 / 45 = 8 units/day.
- C's efficiency = 360 / 120 = 3 units/day.
Let X be the total number of days taken to complete the work.
- B worked for X−5 days (since B left 5 days before completion).
- C worked for X days.
The total work done by A, B, and C can be expressed as:
18(X−10)+8(X−5)+3X=360
Expanding the equation:
18X−180+8X−40+3X=360
(18X+8X+3X)−220=360
29X−220=360
Add 220 to both sides:
29X=580
X=58029
X=20
The total work is completed in 20 days.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Essay Type Question
5 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - TEST YOUR CONCEPTS (Very Short Answer Type Questions)
30 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View Solution
Knowledge Check
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
A9 daysB15 daysC12 daysD14 daysA, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?
A7B10C12D9
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View SolutionA, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?
View Solution