A can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.
The correct Answer is:6
To solve the problem step by step, we will calculate the amount of work done by A and B, and then determine how long they worked together before B left.
Step 1: Calculate the work rates of A and B
- A can complete the work in 20 days, so A's work rate is:
Work rate of A=120 (work per day)
- B can complete the work in 30 days, so B's work rate is:
Work rate of B=130 (work per day)
Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined work rate=120+130
- To add these fractions, find a common denominator. The least common multiple of 20 and 30 is 60:
120=360,130=260
- Therefore, the combined work rate is:
Combined work rate=360+260=560=112 (work per day)
Step 3: Determine the total work done by A in 10 days
- A completes the remaining work in 10 days. Since A's work rate is 120, the amount of work A does in 10 days is:
Work done by A in 10 days=10×120=1020=12 of the total work
Step 4: Calculate the total work
- If A completed 12 of the total work in 10 days, then the total work can be represented as:
Total work=1 (whole work)
Step 5: Determine the work done before B leaves
- Since A completed 12 of the work alone, the other half must have been completed by A and B together. Thus, the work done by A and B together is:
Work done by A and B together=1−12=12
Step 6: Calculate the time they worked together
- Let T be the number of days they worked together. The work done by A and B together in T days is:
T×112=12
- Solving for T:
T=1/21/12=12×121=6 days
Final Answer
- A and B worked together for 6 days.
---
- A can complete the work in 20 days, so A's work rate is:
Work rate of A=120 (work per day)
- B can complete the work in 30 days, so B's work rate is:
Work rate of B=130 (work per day)
- When A and B work together, their combined work rate is:
Combined work rate=120+130
- To add these fractions, find a common denominator. The least common multiple of 20 and 30 is 60:
120=360,130=260
- Therefore, the combined work rate is:
Combined work rate=360+260=560=112 (work per day)
- A completes the remaining work in 10 days. Since A's work rate is 120, the amount of work A does in 10 days is:
Work done by A in 10 days=10×120=1020=12 of the total work
- If A completed 12 of the total work in 10 days, then the total work can be represented as:
Total work=1 (whole work)
- Since A completed 12 of the work alone, the other half must have been completed by A and B together. Thus, the work done by A and B together is:
Work done by A and B together=1−12=12
- Let T be the number of days they worked together. The work done by A and B together in T days is:
T×112=12
- Solving for T:
T=1/21/12=12×121=6 days
- A and B worked together for 6 days.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Essay Type Question
5 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - TEST YOUR CONCEPTS (Very Short Answer Type Questions)
30 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.
View SolutionRajan can do a piece of work in 24 days while Amit can do it in 30 days. In how many days can they complete it they work together?
View Solution
Knowledge Check
A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?
A70 daysB4234 daysC2717daysD1717 daysA can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
A10.5B8C283D9A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
A10.5B8C8.4D9
A can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionA can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
View SolutionA can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
View SolutionA can do a piece of work in 10 days and B can dothe same piece of work in 20 days. They start the work together but after 5 days A leaves off. B will do the remaining piece of work in..
View Solution