A can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:6


To solve the problem step by step, we will calculate the amount of work done by A and B, and then determine how long they worked together before B left.

Step 1: Calculate the work rates of A and B
- A can complete the work in 20 days, so A's work rate is:
Work rate of A=120 (work per day)
- B can complete the work in 30 days, so B's work rate is:
Work rate of B=130 (work per day)

Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined work rate=120+130
- To add these fractions, find a common denominator. The least common multiple of 20 and 30 is 60:
120=360,130=260
- Therefore, the combined work rate is:
Combined work rate=360+260=560=112 (work per day)

Step 3: Determine the total work done by A in 10 days
- A completes the remaining work in 10 days. Since A's work rate is 120, the amount of work A does in 10 days is:
Work done by A in 10 days=10×120=1020=12 of the total work

Step 4: Calculate the total work
- If A completed 12 of the total work in 10 days, then the total work can be represented as:
Total work=1 (whole work)

Step 5: Determine the work done before B leaves
- Since A completed 12 of the work alone, the other half must have been completed by A and B together. Thus, the work done by A and B together is:
Work done by A and B together=112=12

Step 6: Calculate the time they worked together
- Let T be the number of days they worked together. The work done by A and B together in T days is:
T×112=12
- Solving for T:
T=1/21/12=12×121=6 days

Final Answer
- A and B worked together for 6 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

    A70 days
    B4234 days
    C2717days
    D1717 days
  • A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?

    A10.5
    B8
    C283
    D9
  • A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?

    A10.5
    B8
    C8.4
    D9