A boy and his mother together can do a piece of work in 24 days while the day, working with his father, can complete it in 18 days. If the mother and father together take 36 days to complete the same work, then find the time in which they can complete the work if all the three work together. Also find the time they would take to complete the job, if they work individually.
The correct Answer is:16 days,1445 days, 144 days, 48 days
To solve the problem, we will first determine the efficiencies of the boy, mother, and father based on the information provided. We will then calculate how long it will take for them to complete the work together and individually.
Step 1: Determine the total work
We will assume the total work is represented in units. The least common multiple (LCM) of the days taken by each pair will give us the total work.
- Boy and Mother together can complete the work in 24 days.
- Boy and Father together can complete the work in 18 days.
- Mother and Father together can complete the work in 36 days.
LCM of 24, 18, and 36:
- The prime factorization is:
- 24 = 2^3 × 3^1
- 18 = 2^1 × 3^2
- 36 = 2^2 × 3^2
- The LCM will take the highest power of each prime:
- LCM = 2^3 × 3^2 = 8 × 9 = 72
So, the total work is 216 units (since we will multiply LCM by 3).
Step 2: Calculate individual efficiencies
Now, we can calculate the efficiencies of each pair:
1. Boy and Mother:
- Work done in one day = Total work / Days = 216 / 24 = 9 units/day
2. Boy and Father:
- Work done in one day = Total work / Days = 216 / 18 = 12 units/day
3. Mother and Father:
- Work done in one day = Total work / Days = 216 / 36 = 6 units/day
Step 3: Set up equations for individual efficiencies
Let:
- Efficiency of Boy = B
- Efficiency of Mother = M
- Efficiency of Father = F
From the above calculations, we can set up the following equations:
1. B + M = 9 (Equation 1)
2. B + F = 12 (Equation 2)
3. M + F = 6 (Equation 3)
Step 4: Solve the equations
We will add all three equations:
- (B + M) + (B + F) + (M + F) = 9 + 12 + 6
- 2B + 2M + 2F = 27
- B + M + F = 27 / 2 = 13.5 (This is the total efficiency of all three working together)
Now, we can find each individual's efficiency:
- From Equation 1: M = 9 - B
- Substitute M in Equation 3: (9 - B) + F = 6
- F = 6 - 9 + B
- F = B - 3
Now substitute F in Equation 2:
- B + (B - 3) = 12
- 2B - 3 = 12
- 2B = 15
- B = 7.5 units/day
Now substitute B back to find M and F:
- M = 9 - 7.5 = 1.5 units/day
- F = 7.5 - 3 = 4.5 units/day
Step 5: Calculate time taken when all three work together
Total efficiency when all three work together:
- Total efficiency = B + M + F = 7.5 + 1.5 + 4.5 = 13.5 units/day
Now, calculate the time taken to complete the work together:
- Time = Total work / Total efficiency = 216 / 13.5 = 16 days
Step 6: Calculate individual times
1. Time taken by Boy alone:
- Time = Total work / Boy's efficiency = 216 / 7.5 = 28.8 days
2. Time taken by Mother alone:
- Time = Total work / Mother's efficiency = 216 / 1.5 = 144 days
3. Time taken by Father alone:
- Time = Total work / Father's efficiency = 216 / 4.5 = 48 days
Final Answers:
- Time taken by Boy, Mother, and Father together = 16 days
- Time taken by Boy alone = 28.8 days
- Time taken by Mother alone = 144 days
- Time taken by Father alone = 48 days
We will assume the total work is represented in units. The least common multiple (LCM) of the days taken by each pair will give us the total work.
- Boy and Father together can complete the work in 18 days.
- Mother and Father together can complete the work in 36 days.
- The prime factorization is:
- 24 = 2^3 × 3^1
- 18 = 2^1 × 3^2
- 36 = 2^2 × 3^2
- The LCM will take the highest power of each prime:
- LCM = 2^3 × 3^2 = 8 × 9 = 72
Now, we can calculate the efficiencies of each pair:
- Work done in one day = Total work / Days = 216 / 24 = 9 units/day
- Work done in one day = Total work / Days = 216 / 18 = 12 units/day
- Work done in one day = Total work / Days = 216 / 36 = 6 units/day
Let:
- Efficiency of Boy = B
- Efficiency of Mother = M
- Efficiency of Father = F
1. B + M = 9 (Equation 1)
2. B + F = 12 (Equation 2)
3. M + F = 6 (Equation 3)
We will add all three equations:
- (B + M) + (B + F) + (M + F) = 9 + 12 + 6
- 2B + 2M + 2F = 27
- B + M + F = 27 / 2 = 13.5 (This is the total efficiency of all three working together)
- From Equation 1: M = 9 - B
- Substitute M in Equation 3: (9 - B) + F = 6
- F = 6 - 9 + B
- F = B - 3
- B + (B - 3) = 12
- 2B - 3 = 12
- 2B = 15
- B = 7.5 units/day
- M = 9 - 7.5 = 1.5 units/day
- F = 7.5 - 3 = 4.5 units/day
Total efficiency when all three work together:
- Total efficiency = B + M + F = 7.5 + 1.5 + 4.5 = 13.5 units/day
- Time = Total work / Total efficiency = 216 / 13.5 = 16 days
1. Time taken by Boy alone:
- Time = Total work / Boy's efficiency = 216 / 7.5 = 28.8 days
- Time = Total work / Mother's efficiency = 216 / 1.5 = 144 days
- Time = Total work / Father's efficiency = 216 / 4.5 = 48 days
- Time taken by Boy, Mother, and Father together = 16 days
- Time taken by Boy alone = 28.8 days
- Time taken by Mother alone = 144 days
- Time taken by Father alone = 48 days
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)
20 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Short Answer Type Questions
15 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A boy and his mother together can do a piece of work in 24 days while the day, working with his father, can complete it in 18 days. If the mother and father together take 36 days to complete the same work, then find the time in which they can complete the work if all the three work together. Also find the time they would take to complete the job, if they work individually.
View SolutionA and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View Solution
Knowledge Check
A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?
A80 daysB100 daysC120 daysD150 daysA and B together can complete a piece complete a piece of work in 12 days , B and C together can complete it in 15 days. If A is twice as good a workman as C, in many days will A alone complete the same work ?
A(A)45B(B)60C(C)75D(D)30A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:
A12 daysB315 daysC16 daysD9313 days
Mayank can do a piece of work in 3 days while Sanjay can do the same work in 4 days. The wage for the full work is 350. If they both work together to complete the work, then find the earnings of Sanjay.
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionP, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
View SolutionP, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
View SolutionSurbhi can do a piece of work in 24 days. She completed 38 of the work and then left it. Amita complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:
View Solution