A can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
The correct Answer is:6 days
To solve the problem step by step, we will follow the reasoning laid out in the video transcript.
Step 1: Determine the total work
Let’s assume the total work is the least common multiple (LCM) of the days A and B take to complete the work. A can complete the work in 20 days and B in 15 days.
Calculation:
- LCM of 20 and 15 = 60 units
Step 2: Calculate the work done by A and B in one day
Now we can find out how much work A and B can do in one day.
For A:
- A's work in one day = Total work / Days taken by A = 60 / 20 = 3 units per day
For B:
- B's work in one day = Total work / Days taken by B = 60 / 15 = 4 units per day
Step 3: Determine the work done by A in 6 days
According to the question, after B leaves, A completes the remaining work in 6 days. We need to find out how much work A does in those 6 days.
Calculation:
- Work done by A in 6 days = A's work per day * 6 = 3 * 6 = 18 units
Step 4: Calculate the remaining work after A's 6 days of work
Now, we can find out how much work is left after A has completed his part in 6 days.
Calculation:
- Remaining work = Total work - Work done by A in 6 days = 60 - 18 = 42 units
Step 5: Set up the equation for the work done by A and B together
Let T be the number of days A and B worked together before B left. The total work done by A and B together is equal to the remaining work.
Equation:
- Work done by A and B together = (A's efficiency + B's efficiency) * T
- 42 = (3 + 4) * T
- 42 = 7T
Step 6: Solve for T
Now we can solve for T.
Calculation:
- T = 42 / 7 = 6 days
Conclusion
B left the work after 6 days.
Let’s assume the total work is the least common multiple (LCM) of the days A and B take to complete the work. A can complete the work in 20 days and B in 15 days.
- LCM of 20 and 15 = 60 units
Now we can find out how much work A and B can do in one day.
- A's work in one day = Total work / Days taken by A = 60 / 20 = 3 units per day
- B's work in one day = Total work / Days taken by B = 60 / 15 = 4 units per day
According to the question, after B leaves, A completes the remaining work in 6 days. We need to find out how much work A does in those 6 days.
- Work done by A in 6 days = A's work per day * 6 = 3 * 6 = 18 units
Now, we can find out how much work is left after A has completed his part in 6 days.
- Remaining work = Total work - Work done by A in 6 days = 60 - 18 = 42 units
Let T be the number of days A and B worked together before B left. The total work done by A and B together is equal to the remaining work.
- Work done by A and B together = (A's efficiency + B's efficiency) * T
- 42 = (3 + 4) * T
- 42 = 7T
Now we can solve for T.
- T = 42 / 7 = 6 days
B left the work after 6 days.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?
View SolutionA can do a piece of work in 10 days and B can do same work in 15 days. Both A and B start the work and after 3 days B left. In how many days will A do the remaining work?
View Solution
Knowledge Check
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
A18,15.,20B30,20,10C10,15,25D15,10,25A can do a piece of work in 10 days and B can do it in 15 days. After they have worked together for 4 days, A does away and B completes the remaining work. In how many days B complete the remaining work ?
A10B5C15D20A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
A15B16C10D12
A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View Solution(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View SolutionA can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View Solution