(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A 16 days, B 48 days, C 24 days


To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the information provided.

Step 1: Determine the total work
Given:
- A + B can complete the work in 12 days.
- B + C can complete the work in 16 days.

To find the total work, we can take the least common multiple (LCM) of the two durations:
- LCM of 12 and 16 is 48.

Thus, the total work is 48 units.

Step 2: Calculate the efficiencies of A + B and B + C
- The efficiency of A + B:
Efficiency of (A+B)=Total WorkDays=4812=4 units/day

- The efficiency of B + C:
Efficiency of (B+C)=Total WorkDays=4816=3 units/day

Step 3: Set up the equations based on the work done
Let:
- Efficiency of A = a
- Efficiency of B = b
- Efficiency of C = c

From the information:
1. a+b=4 (from A + B)
2. b+c=3 (from B + C)

Step 4: Calculate the work done by A, B, and C
- A works for 5 days:
Work done by A=5a

- B works for 7 days:
Work done by B=7b

- C completes the remaining work in 13 days:
Work done by C=13c

Step 5: Set up the equation for total work
The total work done by A, B, and C should equal the total work:
5a+7b+13c=48

Step 6: Substitute the values of a and b
From the equations:
1. a+b=4a=4b
2. Substitute a in the total work equation:
5(4b)+7b+13c=48
Simplifying this gives:
205b+7b+13c=48
2b+13c=28

Step 7: Substitute c from b+c=3
From b+c=3:
c=3b
Substituting c in the equation 2b+13c=28:
2b+13(3b)=28
Expanding this gives:
2b+3913b=28
Combining like terms:
11b+39=28
11b=2839
11b=11
b=1

Step 8: Find a and c
Using b=1:
- From a+b=4:
a=41=3

- From b+c=3:
c=31=2

Step 9: Calculate the time taken by A, B, and C to complete the work alone
- Time taken by A:
Time=Total WorkEfficiency=483=16 days

- Time taken by B:
Time=481=48 days

- Time taken by C:
Time=482=24 days

Final Answer
- A can complete the work alone in 16 days.
- B can complete the work alone in 48 days.
- C can complete the work alone in 24 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • (A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

    A18,15.,20
    B30,20,10
    C10,15,25
    D15,10,25
  • A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?

    A48
    B60
    C24
    D30
  • A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62