(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
The correct Answer is:A16 days, B48 days, C 24 days
To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the information provided.
Step 1: Determine the total work
Given:
- A + B can complete the work in 12 days.
- B + C can complete the work in 16 days.
To find the total work, we can take the least common multiple (LCM) of the two durations:
- LCM of 12 and 16 is 48.
Thus, the total work is 48 units.
Step 2: Calculate the efficiencies of A + B and B + C
- The efficiency of A + B:
Efficiency of (A+B)=Total WorkDays=4812=4 units/day
- The efficiency of B + C:
Efficiency of (B+C)=Total WorkDays=4816=3 units/day
Step 3: Set up the equations based on the work done
Let:
- Efficiency of A = a
- Efficiency of B = b
- Efficiency of C = c
From the information:
1. a+b=4 (from A + B)
2. b+c=3 (from B + C)
Step 4: Calculate the work done by A, B, and C
- A works for 5 days:
Work done by A=5a
- B works for 7 days:
Work done by B=7b
- C completes the remaining work in 13 days:
Work done by C=13c
Step 5: Set up the equation for total work
The total work done by A, B, and C should equal the total work:
5a+7b+13c=48
Step 6: Substitute the values of a and b
From the equations:
1. a+b=4 → a=4−b
2. Substitute a in the total work equation:
5(4−b)+7b+13c=48
Simplifying this gives:
20−5b+7b+13c=48
2b+13c=28
Step 7: Substitute c from b+c=3
From b+c=3:
c=3−b
Substituting c in the equation 2b+13c=28:
2b+13(3−b)=28
Expanding this gives:
2b+39−13b=28
Combining like terms:
−11b+39=28
−11b=28−39
−11b=−11
b=1
Step 8: Find a and c
Using b=1:
- From a+b=4:
a=4−1=3
- From b+c=3:
c=3−1=2
Step 9: Calculate the time taken by A, B, and C to complete the work alone
- Time taken by A:
Time=Total WorkEfficiency=483=16 days
- Time taken by B:
Time=481=48 days
- Time taken by C:
Time=482=24 days
Final Answer
- A can complete the work alone in 16 days.
- B can complete the work alone in 48 days.
- C can complete the work alone in 24 days.
Given:
- A + B can complete the work in 12 days.
- B + C can complete the work in 16 days.
- LCM of 12 and 16 is 48.
- The efficiency of A + B:
Efficiency of (A+B)=Total WorkDays=4812=4 units/day
Efficiency of (B+C)=Total WorkDays=4816=3 units/day
Let:
- Efficiency of A = a
- Efficiency of B = b
- Efficiency of C = c
1. a+b=4 (from A + B)
2. b+c=3 (from B + C)
- A works for 5 days:
Work done by A=5a
Work done by B=7b
Work done by C=13c
The total work done by A, B, and C should equal the total work:
5a+7b+13c=48
From the equations:
1. a+b=4 → a=4−b
2. Substitute a in the total work equation:
5(4−b)+7b+13c=48
Simplifying this gives:
20−5b+7b+13c=48
2b+13c=28
From b+c=3:
c=3−b
Substituting c in the equation 2b+13c=28:
2b+13(3−b)=28
Expanding this gives:
2b+39−13b=28
Combining like terms:
−11b+39=28
−11b=28−39
−11b=−11
b=1
Using b=1:
- From a+b=4:
a=4−1=3
c=3−1=2
- Time taken by A:
Time=Total WorkEfficiency=483=16 days
Time=481=48 days
Time=482=24 days
- A can complete the work alone in 16 days.
- B can complete the work alone in 48 days.
- C can complete the work alone in 24 days.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View Solution(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View Solution
Knowledge Check
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
A18,15.,20B30,20,10C10,15,25D15,10,25A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
A48B60C24D30A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62
A can do a piece of work in 80 days. A works for 10 days, then B complete the remaining work in 42 days. In how many days will (A + B) do this work together
View SolutionA work for 2 days, then B complete the remaining work in 9 days. If A work for 3 days, then B complete the remaining work in 6 days. In how many days will A and B do this work alone ?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
View Solution