A work for 2 days, then B complete the remaining work in 9 days. If A work for 3 days, then B complete the remaining work in 6 days. In how many days will A and B do this work alone ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A 5 days, B 15 days


To solve the problem step by step, we will denote the efficiencies of A and B as follows:

- Let A's efficiency = 3k units of work per day
- Let B's efficiency = k units of work per day

Step 1: Set up the equations based on the work done
From the problem, we have two scenarios:

1. A works for 2 days, then B completes the remaining work in 9 days.
2. A works for 3 days, then B completes the remaining work in 6 days.

Using these scenarios, we can set up the equations.

Equation 1:
2×(3k)+9×k=Total Work
This simplifies to:
6k+9k=15k(Total Work)

Equation 2:
3×(3k)+6×k=Total Work
This simplifies to:
9k+6k=15k(Total Work)

Step 2: Equate the two equations
Since both equations represent the total work, we can equate them:
6k+9k=9k+6k
This confirms that both scenarios yield the same total work of 15k units.

Step 3: Find the time taken by A and B to complete the work alone
Now we will calculate how many days A and B will take to complete the total work of 15k units alone.

Time taken by A:
Time taken by A=Total WorkEfficiency of A=15k3k=5 days

Time taken by B:
Time taken by B=Total WorkEfficiency of B=15kk=15 days

Conclusion
- A can complete the work alone in 5 days.
- B can complete the work alone in 15 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • (A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

    A18,15.,20
    B30,20,10
    C10,15,25
    D15,10,25
  • A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62
  • A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?

    A48
    B60
    C24
    D30