A work for 2 days, then B complete the remaining work in 9 days. If A work for 3 days, then B complete the remaining work in 6 days. In how many days will A and B do this work alone ?
The correct Answer is:A → 5 days, B →15 days
To solve the problem step by step, we will denote the efficiencies of A and B as follows:
- Let A's efficiency = 3k units of work per day
- Let B's efficiency = k units of work per day
Step 1: Set up the equations based on the work done
From the problem, we have two scenarios:
1. A works for 2 days, then B completes the remaining work in 9 days.
2. A works for 3 days, then B completes the remaining work in 6 days.
Using these scenarios, we can set up the equations.
Equation 1:
2×(3k)+9×k=Total Work
This simplifies to:
6k+9k=15k(Total Work)
Equation 2:
3×(3k)+6×k=Total Work
This simplifies to:
9k+6k=15k(Total Work)
Step 2: Equate the two equations
Since both equations represent the total work, we can equate them:
6k+9k=9k+6k
This confirms that both scenarios yield the same total work of 15k units.
Step 3: Find the time taken by A and B to complete the work alone
Now we will calculate how many days A and B will take to complete the total work of 15k units alone.
Time taken by A:
Time taken by A=Total WorkEfficiency of A=15k3k=5 days
Time taken by B:
Time taken by B=Total WorkEfficiency of B=15kk=15 days
Conclusion
- A can complete the work alone in 5 days.
- B can complete the work alone in 15 days.
- Let B's efficiency = k units of work per day
From the problem, we have two scenarios:
2. A works for 3 days, then B completes the remaining work in 6 days.
2×(3k)+9×k=Total Work
This simplifies to:
6k+9k=15k(Total Work)
3×(3k)+6×k=Total Work
This simplifies to:
9k+6k=15k(Total Work)
Since both equations represent the total work, we can equate them:
6k+9k=9k+6k
This confirms that both scenarios yield the same total work of 15k units.
Now we will calculate how many days A and B will take to complete the total work of 15k units alone.
Time taken by A=Total WorkEfficiency of A=15k3k=5 days
Time taken by B=Total WorkEfficiency of B=15kk=15 days
- A can complete the work alone in 5 days.
- B can complete the work alone in 15 days.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 80 days. A works for 10 days, then B complete the remaining work in 42 days. In how many days will (A + B) do this work together
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View Solution
Knowledge Check
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
A18,15.,20B30,20,10C10,15,25D15,10,25A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
A48B60C24D30
A can do 34th part of a work in 10 days and B completed the remaining part of work in 5 days. In how many days A and B working together will finish that work?
View SolutionA and C started doing a work . After working for 6 days , both left and B alone completed the remaining work in 4 days .In how many days can C alone complete a work in 2 days , then in how many days can A alone complete the work ?
View SolutionA can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View SolutionA can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?
View Solution