A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
60 days
36 days
45 days
24 days
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Determine the combined work rate of A and B
A and B together can complete the work in 12 days. Therefore, their combined work rate (work done per day) can be calculated as:
Combined work rate=1 work12 days=112 work per day
Step 2: Express the work rates of A and B
Let the work rate of A be A (units of work per day) and the work rate of B be B (units of work per day). From the combined work rate, we have:
A+B=112
Step 3: Calculate the work done by A in 8 days
If A works alone for 8 days, the amount of work done by A is:
Work done by A in 8 days=8A
Step 4: Determine the remaining work
The remaining work after A has worked for 8 days can be expressed as:
Remaining work=1−8A
Step 5: Calculate the work done by B in 20 days
B alone can complete the remaining work in 20 days, so we can express this as:
Work done by B in 20 days=20B
Since this work is equal to the remaining work, we have:
20B=1−8A
Step 6: Set up the equations
Now we have two equations:
1. A+B=112
2. 20B=1−8A
Step 7: Substitute A from the first equation into the second
From the first equation, we can express A in terms of B:
A=112−B
Substituting this into the second equation gives:
20B=1−8(112−B)
Simplifying this:
20B=1−812+8B
20B=1−23+8B
20B=33−23+8B
20B=13+8B
Step 8: Solve for B
Now, isolate B:
20B−8B=13
12B=13
B=136
Step 9: Find the work rate of A
Now substituting B back to find A:
A+136=112
A=112−136
Finding a common denominator (36):
A=336−136=236=118
Step 10: Calculate the total work
The total work can be calculated as:
Total work=(A + B) work rate×time=(112)×12=1 work unit
Step 11: Determine how many days B alone can complete the whole work
Since B's work rate is 136 work units per day, the total time for B to complete the whole work is:
Time=1 workB=1136=36 days
Final Answer
B alone can complete the whole work in 36 days.
---
A and B together can complete the work in 12 days. Therefore, their combined work rate (work done per day) can be calculated as:
Combined work rate=1 work12 days=112 work per day
Let the work rate of A be A (units of work per day) and the work rate of B be B (units of work per day). From the combined work rate, we have:
A+B=112
If A works alone for 8 days, the amount of work done by A is:
Work done by A in 8 days=8A
The remaining work after A has worked for 8 days can be expressed as:
Remaining work=1−8A
B alone can complete the remaining work in 20 days, so we can express this as:
Work done by B in 20 days=20B
Since this work is equal to the remaining work, we have:
20B=1−8A
Now we have two equations:
1. A+B=112
2. 20B=1−8A
From the first equation, we can express A in terms of B:
A=112−B
Substituting this into the second equation gives:
20B=1−8(112−B)
Simplifying this:
20B=1−812+8B
20B=1−23+8B
20B=33−23+8B
20B=13+8B
Now, isolate B:
20B−8B=13
12B=13
B=136
Now substituting B back to find A:
A+136=112
A=112−136
Finding a common denominator (36):
A=336−136=236=118
The total work can be calculated as:
Total work=(A + B) work rate×time=(112)×12=1 work unit
Since B's work rate is 136 work units per day, the total time for B to complete the whole work is:
Time=1 workB=1136=36 days
B alone can complete the whole work in 36 days.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
View SolutionA alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
View Solution
Knowledge Check
U, V and W together can complete a work in 10 days. If U alone can complete the work in 20 days and V alone can complete the work in 30 days, then in how many days W alone can complete the work?
AA)30BB)40CC)60DD)80If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?
A24 daysB15 daysC8 daysD18 daysIf Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?
A96 daysB128 daysC64 daysD118 days
C alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View SolutionA alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
View SolutionP and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
View Solution