A can do a work in 6 days, B can do it in 8 days and C can complete it in 12 days. If A starts the work and they work in alternatively, then in how many days, the work will be completed?
635
723
525
623
The correct Answer is:B
To solve the problem, we need to determine how many days A, B, and C will take to complete the work when they work alternately. Here's the step-by-step solution:
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 6 days, so A's work rate is 16 of the work per day.
- B can complete the work in 8 days, so B's work rate is 18 of the work per day.
- C can complete the work in 12 days, so C's work rate is 112 of the work per day.
Step 2: Calculate the total work done in a 3-day cycle.
In a 3-day cycle:
- Day 1: A works and completes 16 of the work.
- Day 2: B works and completes 18 of the work.
- Day 3: C works and completes 112 of the work.
Now, we find the total work done in these 3 days:
Total work in 3 days=16+18+112
Step 3: Find a common denominator and sum the fractions.
The least common multiple (LCM) of 6, 8, and 12 is 24. We convert each fraction:
- 16=424
- 18=324
- 112=224
Now, adding these fractions:
Total work in 3 days=424+324+224=924=38
Step 4: Calculate how many such cycles are needed to complete the work.
To complete the entire work (1 unit of work), we need to find how many cycles of 3 days are required:
Number of cycles=138=83
This means they will complete the work in 2 full cycles (which is 6 days) and will have some work remaining.
Step 5: Calculate the remaining work after 2 cycles.
In 2 cycles (6 days), the work done is:
Work done in 6 days=2×38=68=34
The remaining work is:
Remaining work=1−34=14
Step 6: Determine who will work next and how long it will take to finish the remaining work.
On the 7th day, A will work again. A can complete 16 of the work in one day. To find out how much time A will take to complete the remaining 14 of the work:
Time taken by A=Remaining workA's work rate=1416=14×6=64=1.5 days
Step 7: Calculate the total time taken.
Total time taken = Time for 2 cycles (6 days) + Time taken by A (1.5 days):
Total time=6+1.5=7.5 days
Final Answer:
The work will be completed in 7.5 days.
- A can complete the work in 6 days, so A's work rate is 16 of the work per day.
- B can complete the work in 8 days, so B's work rate is 18 of the work per day.
- C can complete the work in 12 days, so C's work rate is 112 of the work per day.
In a 3-day cycle:
- Day 1: A works and completes 16 of the work.
- Day 2: B works and completes 18 of the work.
- Day 3: C works and completes 112 of the work.
Total work in 3 days=16+18+112
The least common multiple (LCM) of 6, 8, and 12 is 24. We convert each fraction:
- 16=424
- 18=324
- 112=224
Total work in 3 days=424+324+224=924=38
To complete the entire work (1 unit of work), we need to find how many cycles of 3 days are required:
Number of cycles=138=83
This means they will complete the work in 2 full cycles (which is 6 days) and will have some work remaining.
In 2 cycles (6 days), the work done is:
Work done in 6 days=2×38=68=34
The remaining work is:
Remaining work=1−34=14
On the 7th day, A will work again. A can complete 16 of the work in one day. To find out how much time A will take to complete the remaining 14 of the work:
Time taken by A=Remaining workA's work rate=1416=14×6=64=1.5 days
Total time taken = Time for 2 cycles (6 days) + Time taken by A (1.5 days):
Total time=6+1.5=7.5 days
The work will be completed in 7.5 days.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 20 days and 25 days. A start the work and they do this work in alternate days. In how many days will this work be completed ?
View SolutionA and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?
View Solution
Knowledge Check
A and B can do a work in 20 days, B and C can do it in 30 days and C and A can complete it in 15 days. If A and B starts the work and on every second day C help them, then in how many days, the work will be completed?
A16B18C26D36A and B can do a work in 20 days, B and C can do it in 30 days and C and A can complete it in 15 days. If A and B starts the work and on every second day C help them, then in how many days, the work will be completed?
A8B16C3D9A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?
A6B4C5D10
A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :
View SolutionA can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
View SolutionA can do a piece of work in 8 days, B can do it in 10 days and C can do it in 20 days. In how many days canA, BandCtogether complete the work?
View Solution