A, B and C can do job in 9, 12 and 36 days respectively if they worked alone. A leaves after they have worked together for 3 days. In how many days can B and C do the rest of the job?
3
4
5
6
The correct Answer is:A
To solve the problem step by step, we will follow the process of calculating the work done by A, B, and C, and then determine how long it will take for B and C to finish the remaining work after A leaves.
Step 1: Determine the work rates of A, B, and C
- A can complete the job in 9 days, so A's work rate is 19 of the job per day.
- B can complete the job in 12 days, so B's work rate is 112 of the job per day.
- C can complete the job in 36 days, so C's work rate is 136 of the job per day.
Step 2: Calculate the combined work rate of A, B, and C
To find the combined work rate when A, B, and C work together, we add their individual work rates:
Combined work rate=19+112+136
To add these fractions, we need a common denominator. The least common multiple (LCM) of 9, 12, and 36 is 36. We can rewrite each fraction:
- 19=436
- 112=336
- 136=136
Now, we can add them:
Combined work rate=436+336+136=836=29
Step 3: Calculate the work done in 3 days
Now that we have the combined work rate, we can find out how much work A, B, and C complete together in 3 days:
Work done in 3 days=Combined work rate×Time=29×3=69=23
Step 4: Determine the remaining work
The total work is considered as 1 (the whole job). After 3 days, the remaining work is:
Remaining work=1−23=13
Step 5: Calculate the combined work rate of B and C
Next, we need to find out how fast B and C can complete the remaining work. Their combined work rate is:
Combined work rate of B and C=112+136
Again, we find a common denominator. The LCM of 12 and 36 is 36:
- 112=336
- 136=136
Now, we can add them:
Combined work rate of B and C=336+136=436=19
Step 6: Calculate the time taken by B and C to finish the remaining work
Now we can find the time it takes for B and C to complete the remaining 13 of the work:
Time=Remaining workCombined work rate of B and C=1319=13×91=3 days
Final Answer
B and C can complete the remaining work in 3 days.
---
- A can complete the job in 9 days, so A's work rate is 19 of the job per day.
- B can complete the job in 12 days, so B's work rate is 112 of the job per day.
- C can complete the job in 36 days, so C's work rate is 136 of the job per day.
To find the combined work rate when A, B, and C work together, we add their individual work rates:
Combined work rate=19+112+136
- 19=436
- 112=336
- 136=136
Combined work rate=436+336+136=836=29
Now that we have the combined work rate, we can find out how much work A, B, and C complete together in 3 days:
Work done in 3 days=Combined work rate×Time=29×3=69=23
The total work is considered as 1 (the whole job). After 3 days, the remaining work is:
Remaining work=1−23=13
Next, we need to find out how fast B and C can complete the remaining work. Their combined work rate is:
Combined work rate of B and C=112+136
- 112=336
- 136=136
Combined work rate of B and C=336+136=436=19
Now we can find the time it takes for B and C to complete the remaining 13 of the work:
Time=Remaining workCombined work rate of B and C=1319=13×91=3 days
B and C can complete the remaining work in 3 days.
Topper's Solved these Questions
Similar Questions
A and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then, the total number of days needed for the completion of the work is
View SolutionA,B andC can do a job working alone in 12, 16 and 24 days, respectively.In how many days, they can do the job, if they worked together?
View Solution
Knowledge Check
- Question 1 - Select One
If A, B and C can do a job working alone in 12, 18 and 36 days respectively. They all work together for 2 day, then B quits. How many days will A and C take to finish rest of the job?
A9B6C3D4 - Question 2 - Select One
A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
A20B30C18D24 - Question 3 - Select One
A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
AA) 20BB) 30CC) 18DD) 24
A and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?
View SolutionA, B and C can do a job working alone in 6, 9 and 18 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to complete the remainder of the job?
View SolutionA and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View SolutionA, B and C can do a job in 6 days, 12 days and 15 days respectively. After 18 of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the remaining work is
View Solution