A, B and C can do job in 9, 12 and 36 days respectively if they worked alone. A leaves after they have worked together for 3 days. In how many days can B and C do the rest of the job?

A

3

B

4

C

5

D

6

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow the process of calculating the work done by A, B, and C, and then determine how long it will take for B and C to finish the remaining work after A leaves.

Step 1: Determine the work rates of A, B, and C
- A can complete the job in 9 days, so A's work rate is 19 of the job per day.
- B can complete the job in 12 days, so B's work rate is 112 of the job per day.
- C can complete the job in 36 days, so C's work rate is 136 of the job per day.

Step 2: Calculate the combined work rate of A, B, and C
To find the combined work rate when A, B, and C work together, we add their individual work rates:
Combined work rate=19+112+136

To add these fractions, we need a common denominator. The least common multiple (LCM) of 9, 12, and 36 is 36. We can rewrite each fraction:
- 19=436
- 112=336
- 136=136

Now, we can add them:
Combined work rate=436+336+136=836=29

Step 3: Calculate the work done in 3 days
Now that we have the combined work rate, we can find out how much work A, B, and C complete together in 3 days:
Work done in 3 days=Combined work rate×Time=29×3=69=23

Step 4: Determine the remaining work
The total work is considered as 1 (the whole job). After 3 days, the remaining work is:
Remaining work=123=13

Step 5: Calculate the combined work rate of B and C
Next, we need to find out how fast B and C can complete the remaining work. Their combined work rate is:
Combined work rate of B and C=112+136

Again, we find a common denominator. The LCM of 12 and 36 is 36:
- 112=336
- 136=136

Now, we can add them:
Combined work rate of B and C=336+136=436=19

Step 6: Calculate the time taken by B and C to finish the remaining work
Now we can find the time it takes for B and C to complete the remaining 13 of the work:
Time=Remaining workCombined work rate of B and C=1319=13×91=3 days

Final Answer
B and C can complete the remaining work in 3 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If A, B and C can do a job working alone in 12, 18 and 36 days respectively. They all work together for 2 day, then B quits. How many days will A and C take to finish rest of the job?

    A9
    B6
    C3
    D4
  • Question 2 - Select One

    A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?

    A20
    B30
    C18
    D24
  • Question 3 - Select One

    A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?

    AA) 20
    BB) 30
    CC) 18
    DD) 24