A, B and C can do a job in 6 days, 12 days and 15 days respectively. After 18 of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the remaining work is

A

556 days

B

614 days

C

312 days

D

334 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we will follow these steps:

Step 1: Calculate the work done by A, B, and C in one day.
- A can complete the work in 6 days, so A's work per day = 16 of the work.
- B can complete the work in 12 days, so B's work per day = 112 of the work.
- C can complete the work in 15 days, so C's work per day = 115 of the work.

Step 2: Find the combined work done by A, B, and C in one day.
- Combined work per day = A's work + B's work + C's work
- Combined work per day = 16+112+115

To add these fractions, we need a common denominator. The least common multiple (LCM) of 6, 12, and 15 is 60.

- 16=1060
- 112=560
- 115=460

Now, adding them together:
- Combined work per day = 1060+560+460=1960

Step 3: Calculate the total work done after 18 of the work is completed.
- Total work can be considered as 1 unit (or 120 units for easier calculation).
- Work completed after 18 of the work = 18 of 120 = 15 units.

Step 4: Calculate the remaining work.
- Remaining work = Total work - Work completed = 120 - 15 = 105 units.

Step 5: Calculate the work done by A and B together.
- A's work per day = 16
- B's work per day = 112
- Combined work per day by A and B = 16+112

Finding a common denominator (which is 12):
- 16=212
- 112=112

Combined work per day by A and B:
- Combined work = 212+112=312=14

Step 6: Calculate the time taken to finish the remaining work.
- Remaining work = 105 units
- Work done by A and B together in one day = 14 of the total work (which is 120 units).

To find how many days it takes to complete 105 units:
- If A and B together do 14 of 120 units in one day, they do 30 units in one day.
- Time taken to finish 105 units = 10530=3.5 days.

Final Answer:
The time taken to finish the remaining work is 3.5 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can do a job in 6 days, 12 days and 15 days respectively. After 18 of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the remaining work is

    A556 days
    B514 days
    C312 days
    D334 days
  • Question 2 - Select One

    A, B and C can do a piece of work in 10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?

    A2days
    B3days
    C5days
    D4days
  • Question 3 - Select One

    A, B and C can do job in 9, 12 and 36 days respectively if they worked alone. A leaves after they have worked together for 3 days. In how many days can B and C do the rest of the job?

    A3
    B4
    C5
    D6