Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take 412 hours more than when work together. The time required to finish the work together is
1. 5 hours
2. 8 hours
3. 4 hours
4. 6 hours
The correct Answer is:D
To solve the problem step by step, we will define the variables and use the information given in the question.
Step 1: Define Variables
Let x be the time taken to complete the work when A and B work together.
Step 2: Express Individual Times
According to the problem:
- A takes x+8 hours to complete the work alone.
- B takes x+4.5 hours to complete the work alone.
Step 3: Calculate Work Rates
The work done in one hour by each worker can be expressed as:
- Work rate of A: 1x+8
- Work rate of B: 1x+4.5
When A and B work together, their combined work rate is:
1x+8+1x+4.5=1x
Step 4: Set Up the Equation
Now, we can set up the equation based on the combined work rate:
1x+8+1x+4.5=1x
Step 5: Clear the Fractions
To eliminate the fractions, we can multiply through by x(x+8)(x+4.5):
x(x+4.5)+x(x+8)=(x+8)(x+4.5)
Step 6: Expand the Equation
Expanding both sides:
- Left side:
x2+4.5x+x2+8x=2x2+12.5x
- Right side:
x2+4.5x+8x+36=x2+12.5x+36
Step 7: Combine Like Terms
Now we have:
2x2+12.5x=x2+12.5x+36
Subtract x2+12.5x from both sides:
2x2−x2+12.5x−12.5x=36
This simplifies to:
x2=36
Step 8: Solve for x
Taking the square root of both sides:
x=6
Conclusion
The time required to finish the work together is 6 hours.
Let x be the time taken to complete the work when A and B work together.
According to the problem:
- A takes x+8 hours to complete the work alone.
- B takes x+4.5 hours to complete the work alone.
The work done in one hour by each worker can be expressed as:
- Work rate of A: 1x+8
- Work rate of B: 1x+4.5
1x+8+1x+4.5=1x
Now, we can set up the equation based on the combined work rate:
1x+8+1x+4.5=1x
To eliminate the fractions, we can multiply through by x(x+8)(x+4.5):
x(x+4.5)+x(x+8)=(x+8)(x+4.5)
Expanding both sides:
- Left side:
x2+4.5x+x2+8x=2x2+12.5x
- Right side:
x2+4.5x+8x+36=x2+12.5x+36
Now we have:
2x2+12.5x=x2+12.5x+36
Subtract x2+12.5x from both sides:
2x2−x2+12.5x−12.5x=36
This simplifies to:
x2=36
Taking the square root of both sides:
x=6
The time required to finish the work together is 6 hours.
Topper's Solved these Questions
Similar Questions
Two workers A and B are engaged to do a piece of work.Working alone, A takes 8 hours more to complete the workthan if both worked together. On the other hand, workingalone, B would need 412 hours more to complete the work than if both worked together. How much time would they take tocomplete the job working together?
View SolutionTushar takes 6 hours to complete a piece of work, while Amar completes the same work in 10 hours. If both of them work together, then what is the time required to complete the work?
View Solution
Knowledge Check
Two workers A and B are engaged to do a piece of work. Working alone, A takes 8 hours more to complete the work than if both worked together. On the other hand, working alone, B would need 412 hours more to complete the work than if both worked together. How much time would they take to complete the job working together?
A4HoursB5HoursC6 HoursD7 HoursA alone takes 4 more days to complete a work, in that time A and B can complete it together and B alone takes 16 more days to complete the same. In how many days they will do it together?
A1. 6B2. 8C3. 12D4. 10A can do a piece of work in 2 hours, B can do thrice the work in 8 hours and C can do the same work as A in 8 hours. If all of them work together, how long it would take them to complete the work :
A1 hourB2 hoursC3 hoursD4 hours
A takes 4 hours more than that of A and B working together to finish certain piece of work. While B takes 9 hours more than that of A and B working together. Then find in how many hours A and B working together can finish the work?
View SolutionWhen A alone does a piece of work , he takes 16 days more than the time taken by (A+B) to complete the work, while B alone takes 9 days more than the time taken by (A + B) to finish the work. What time,AandBtogether will take to finish this work?
View SolutionA and B working together can do a piece of work in 12 days and A alone can caomplete the work in 18 days. How long will B alone take to complete the job?
View SolutionA can do a piece of work in 2 hours, B can do thrice the work in 8 hours and C can do the same work as A in 8 hours. If all of them work together, how long it would take them to complete the work :
View SolutionSunny and Paula can complete a piece of work together in 12 hours. While Paula takes 18 hours to complete the work 2 alone, another individual, Jane, takes 45 hours to complete the same piece of work alone. How many hours would it take Sunny and Jane to complete the same work together ?
View Solution