A group of persons can do a work in 10 days. If 5 persons remains absent from first day, then the work is completed in 12 days by remaining persons. Tell how many persons were in the group initially?
1. 20
2. 25
3. 45
4. 30
The correct Answer is:D
To solve the problem step-by-step, we will use the relationship between the number of workers, the number of days they work, and the total work done.
Step 1: Define Variables
Let the initial number of persons in the group be X.
Step 2: Calculate Total Work
The total work can be expressed in terms of the number of persons and the number of days. If X persons can complete the work in 10 days, then the total work W can be calculated as:
W=X×10
Step 3: Work Done with Absentees
If 5 persons are absent, then the number of persons working becomes X−5. According to the problem, the remaining persons complete the work in 12 days. Therefore, the total work can also be expressed as:
W=(X−5)×12
Step 4: Set the Equations Equal
Since both expressions represent the same total work W, we can set them equal to each other:
X×10=(X−5)×12
Step 5: Expand and Rearrange the Equation
Expanding the right side gives:
10X=12X−60
Now, rearranging the equation to isolate X:
10X−12X=−60
−2X=−60
2X=60
Step 6: Solve for X
Dividing both sides by 2 gives:
X=30
Conclusion
Thus, the initial number of persons in the group is 30.
Let the initial number of persons in the group be X.
The total work can be expressed in terms of the number of persons and the number of days. If X persons can complete the work in 10 days, then the total work W can be calculated as:
W=X×10
If 5 persons are absent, then the number of persons working becomes X−5. According to the problem, the remaining persons complete the work in 12 days. Therefore, the total work can also be expressed as:
W=(X−5)×12
Since both expressions represent the same total work W, we can set them equal to each other:
X×10=(X−5)×12
Expanding the right side gives:
10X=12X−60
Now, rearranging the equation to isolate X:
10X−12X=−60
−2X=−60
2X=60
Dividing both sides by 2 gives:
X=30
Thus, the initial number of persons in the group is 30.
Topper's Solved these Questions
Similar Questions
A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
View SolutionA certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
View Solution
Knowledge Check
Some person can do nay work in 60 days. If 8 person were more, than the work has been finished 10 days before. How many persons were there in starting ?
A40B50C25D30If 3 persons can do a piece of work in 4 days, then 4 persons can do it in …… days.
A1B2C3D4a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?
A17B24C30D22
If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
View SolutionIf 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
View Solution25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?
View Solution12 persons can complete half of a work in 9 days. How many persons can complete the same work (whole) in 6 days?
View SolutionTwo persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View Solution