If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
40
20
14
10
The correct Answer is:B
To solve the problem, we need to determine how many persons are required to complete the same piece of work in 28 days, given that 40 persons can complete it in 14 days.
1. Calculate the Total Work Done in Person-Days:
The total work can be calculated in terms of person-days. If 40 persons can complete the work in 14 days, we can find the total work in person-days as follows:
Total Work=Number of Persons×Number of Days=40×14=560 person-days
2. Determine the Number of Persons Required for 28 Days:
Now, we want to find out how many persons (let's denote this as x) are needed to complete the same work in 28 days. We can set up the equation:
Total Work=Number of Persons×Number of Days
Substituting the known values:
560=x×28
3. Solve for x:
To find x, we can rearrange the equation:
x=56028
Now, perform the division:
x=20
Thus, the number of persons required to complete the work in 28 days is 20.
Final Answer:
The number of persons required to complete the work in 28 days is 20.
---
The total work can be calculated in terms of person-days. If 40 persons can complete the work in 14 days, we can find the total work in person-days as follows:
Total Work=Number of Persons×Number of Days=40×14=560 person-days
Now, we want to find out how many persons (let's denote this as x) are needed to complete the same work in 28 days. We can set up the equation:
Total Work=Number of Persons×Number of Days
Substituting the known values:
560=x×28
To find x, we can rearrange the equation:
x=56028
Now, perform the division:
x=20
The number of persons required to complete the work in 28 days is 20.
Topper's Solved these Questions
Similar Questions
Knowledge Check
If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
A4B5C14D10If 5 men can do a piece of work in 28 days then the number of persons required to the same work in 7 days is :
A15B30C20D3530 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?
A4B5C6Dnone of these
Some persons can do piece of work in 12 days. Two times the number of such persons will do half of the work in
(A) 9 days (B) 6 days (C) 5 days (D) 3 days
View Solution12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time? 144 b. 190 c. 180 d. 192
View Solution15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?
View SolutionSome persons can do a piece of work in 12 days. Two times the number of such persons will do half of the work in
View Solution12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?
View Solution