42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

A

7

B

6

C

14

D

16

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will calculate the total work done, determine how many workers are needed to complete the work in the desired time, and then find out how many extra workers are required.

Step 1: Calculate the Total Work
The total work can be calculated using the formula:
Total Work=Number of Workers×Number of Days

Given:
- Number of Workers = 42
- Number of Days = 8

Now, substituting the values:
Total Work=42×8=336 units

Step 2: Determine the Number of Workers Needed for 7 Days
Now, we need to find out how many workers are required to complete the same amount of work (336 units) in 7 days. We can rearrange the formula:
Number of Workers=Total WorkNumber of Days

Substituting the values:
Number of Workers=3367=48 workers

Step 3: Calculate the Extra Workers Needed
To find the extra workers needed, we subtract the original number of workers from the number of workers required to complete the work in 7 days:
Extra Workers=Workers NeededOriginal Workers

Substituting the values:
Extra Workers=4842=6 extra workers

Conclusion
Therefore, the number of extra workers needed to complete the work in 7 days is 6.

---

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

    A7
    B8
    C14
    D16
  • 56 workers canfinish a piece of work in 14 days. If the work
    is to be completed in 8 days, then how many extra workers
    are required ?

    A36
    B48
    C44
    D42
  • In a field 6 workers complete a task in 16 days.If this task is to be completed in 4 days,then how many workers will be required?

    A20
    B14
    C24
    D28