42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
7
6
14
16
The correct Answer is:B
To solve the problem step by step, we will calculate the total work done, determine how many workers are needed to complete the work in the desired time, and then find out how many extra workers are required.
Step 1: Calculate the Total Work
The total work can be calculated using the formula:
Total Work=Number of Workers×Number of Days
Given:
- Number of Workers = 42
- Number of Days = 8
Now, substituting the values:
Total Work=42×8=336 units
Step 2: Determine the Number of Workers Needed for 7 Days
Now, we need to find out how many workers are required to complete the same amount of work (336 units) in 7 days. We can rearrange the formula:
Number of Workers=Total WorkNumber of Days
Substituting the values:
Number of Workers=3367=48 workers
Step 3: Calculate the Extra Workers Needed
To find the extra workers needed, we subtract the original number of workers from the number of workers required to complete the work in 7 days:
Extra Workers=Workers Needed−Original Workers
Substituting the values:
Extra Workers=48−42=6 extra workers
Conclusion
Therefore, the number of extra workers needed to complete the work in 7 days is 6.
---
The total work can be calculated using the formula:
Total Work=Number of Workers×Number of Days
- Number of Workers = 42
- Number of Days = 8
Total Work=42×8=336 units
Now, we need to find out how many workers are required to complete the same amount of work (336 units) in 7 days. We can rearrange the formula:
Number of Workers=Total WorkNumber of Days
Number of Workers=3367=48 workers
To find the extra workers needed, we subtract the original number of workers from the number of workers required to complete the work in 7 days:
Extra Workers=Workers Needed−Original Workers
Extra Workers=48−42=6 extra workers
Therefore, the number of extra workers needed to complete the work in 7 days is 6.
Topper's Solved these Questions
Similar Questions
Knowledge Check
56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
A7B8C14D1656 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?A36B48C44D42In a field 6 workers complete a task in 16 days.If this task is to be completed in 4 days,then how many workers will be required?
A20B14C24D28
30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days if all the 30 workers started the work.
View Solution14 workers can build a wall in 42 days. One worker can build it in
View SolutionA can do a work in 21 days and B in 42 days. If they work on it together for 7 days, then what fraction of work is left?
View SolutionA can do a work in 21 days and B in 42 days. If they work on it together for 7 days, then what fraction of work is left?
View Solution12 men can reap a field in 25 days. In how many days can 20 men reap the same field?
View Solution