30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days if all the 30 workers started the work.
12
10
6
none of these
The correct Answer is:C
To solve the problem step by step, we will follow these steps:
Step 1: Understand the Problem
We know that 30 workers can complete a job in 20 days. We need to find out after how many days 9 workers should leave the job so that the total work is completed in 26 days.
Step 2: Calculate Total Work
First, we calculate the total amount of work in terms of worker-days.
- Total work (W) = Number of workers × Number of days = 30 workers × 20 days = 600 worker-days.
Step 3: Define Variables
Let X be the number of days after which 9 workers leave the job. This means that for the first X days, all 30 workers are working.
Step 4: Calculate Work Done in First X Days
The work done by 30 workers in X days is:
- Work done = Number of workers × Number of days = 30 workers × X days = 30X worker-days.
Step 5: Calculate Remaining Work
The total work is 600 worker-days. The remaining work after X days is:
- Remaining work = Total work - Work done in first X days = 600−30X.
Step 6: Determine Remaining Days
After X days, the total time to complete the work is 26 days. Therefore, the remaining days after X days is:
- Remaining days = Total days - Days worked = 26−X.
Step 7: Calculate Work Done by Remaining Workers
After X days, 21 workers (30 - 9) will continue the work for 26−X days. The work done by these 21 workers is:
- Work done = Number of workers × Number of days = 21 workers × (26−X) days = 21(26−X) worker-days.
Step 8: Set Up the Equation
The total work done must equal the total work required:
30X+21(26−X)=600.
Step 9: Solve the Equation
Expanding the equation:
30X+546−21X=600.
Combine like terms:
9X+546=600.
Subtract 546 from both sides:
9X=54.
Divide by 9:
X=6.
Conclusion
Thus, 9 workers should leave the job after 6 days.
We know that 30 workers can complete a job in 20 days. We need to find out after how many days 9 workers should leave the job so that the total work is completed in 26 days.
First, we calculate the total amount of work in terms of worker-days.
- Total work (W) = Number of workers × Number of days = 30 workers × 20 days = 600 worker-days.
Let X be the number of days after which 9 workers leave the job. This means that for the first X days, all 30 workers are working.
The work done by 30 workers in X days is:
- Work done = Number of workers × Number of days = 30 workers × X days = 30X worker-days.
The total work is 600 worker-days. The remaining work after X days is:
- Remaining work = Total work - Work done in first X days = 600−30X.
After X days, the total time to complete the work is 26 days. Therefore, the remaining days after X days is:
- Remaining days = Total days - Days worked = 26−X.
After X days, 21 workers (30 - 9) will continue the work for 26−X days. The work done by these 21 workers is:
- Work done = Number of workers × Number of days = 21 workers × (26−X) days = 21(26−X) worker-days.
The total work done must equal the total work required:
30X+21(26−X)=600.
Expanding the equation:
30X+546−21X=600.
Combine like terms:
9X+546=600.
Subtract 546 from both sides:
9X=54.
Divide by 9:
X=6.
Thus, 9 workers should leave the job after 6 days.
Topper's Solved these Questions
Similar Questions
30 persons can finish a job in20 days. After 6 days how many persons should leave the job, so that work is completedina total of 26 days?
View SolutionA, B and C can finish a piece of work in 20 days, 25 days and 30 days respectively. They started working together. After how many days A should leave the work so that total work will be complete in 12 days?
View Solution
Knowledge Check
30 girls can finish a work in 40 days. After how many days should 10 girls leave the work so that it may be finished in 46 days, if all the 30 girls started the work?
A18 daysB28 daysC22 daysD30 days30 girls can finish a work in 40 days. After how many days should 10 girls leave the work so that it may be finished in 46 days, if all the 30 girls started the work?
A18 daysB28 daysC22 daysD30 days100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
A100B60C80D40
56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View Solution42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View Solution25 men can complete a job in 30 days. After how many days should the strength of work force be increased by 50 men so that the work will be completed 23rd in of the actual time:
View SolutionIf 60 boys can finish a work in 15 days by working 8 hours a day, then how many hours a day should 72 boys work to finish that work within 20 days?
View SolutionIf 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.
View Solution