A and C can finish a work in 40 days. They worked at it for 10 days and then A left. The remaining work is done by C alone in 30 more days. How long will it take C to finish the work alone?

A

30 days

B

22 days

C

40 days

D

25 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break it down:

Step 1: Determine the combined work rate of A and C
A and C can finish the work together in 40 days. This means their combined work rate is:
Work rate of A + C=1 unit of work40 days=140 units per day

Hint: Remember that the work rate is calculated as the total work done divided by the time taken.

Step 2: Calculate the work done by A and C in 10 days
In 10 days, A and C will complete:
Work done in 10 days=Work rate×Time=140×10=1040=14 units

Hint: Multiply the work rate by the number of days to find the total work completed.

Step 3: Determine the remaining work
Since they completed 14 of the work, the remaining work is:
Remaining work=114=34 units

Hint: Subtract the completed work from the total work to find out how much is left.

Step 4: Find out how long C takes to finish the remaining work
C completes the remaining 34 units of work in 30 days. Therefore, C's work rate can be calculated as:
Work rate of C=Work doneTime=3430=3120=140 units per day

Hint: Use the formula for work rate (work done divided by time) to find C's efficiency.

Step 5: Calculate how long it will take C to finish the work alone
Since C's work rate is 140 units per day, the time taken by C to complete 1 unit of work is:
Time taken by C=1 unit140 units per day=40 days

Hint: To find the time taken for one unit of work, take the reciprocal of the work rate.

Conclusion
C will take 40 days to finish the work alone.

Final Answer: 40 days

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • P and Q can finish a work in 30 days. They worked at it for 10 days and then Q left. The remaining work is done byPalone in 20 more days. How long willPtake to finish the work alone?

    A30 days
    B20 days
    C60 days
    D50 days
  • A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…

    A48 days
    B50 days
    C54 days
    D60 days
  • A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?

    A60
    B50
    C40
    D30