If 20 engineers and 20 workers can together construct a 20 km road in 20 days. 40 engineers and 40 workers together construct 40 km road in how many days?
10
20
40
can’t be determined
The correct Answer is:B
To solve the problem step by step, we will first determine the work done by the engineers and workers in the first scenario and then use that information to find out how many days it will take for the second scenario.
Step 1: Determine the total work done in the first scenario
We know that:
- 20 engineers and 20 workers can construct a 20 km road in 20 days.
Total work done (in km) = 20 km
Total time taken = 20 days
Step 2: Calculate the work done per day
The work done per day by 20 engineers and 20 workers:
Work per day=Total workTotal time=20 km20 days=1 km/day
Step 3: Calculate the work done by one engineer and one worker
Since 20 engineers and 20 workers together do 1 km of work in a day, we can express this as:
Work done by 20 engineers and 20 workers in one day=1 km
Let the work done by one engineer in one day be e km and the work done by one worker in one day be w km. Therefore:
20e+20w=1 km
Dividing the entire equation by 20:
e+w=120 km
Step 4: Analyze the second scenario
Now, we need to find out how many days it will take for 40 engineers and 40 workers to construct a 40 km road.
Total work required = 40 km
Let d be the number of days required.
The work done by 40 engineers and 40 workers in one day:
40e+40w
We can factor out 40:
40(e+w)=40×120=2 km/day
Step 5: Calculate the number of days required
Now, we need to find d such that:
Total work=Work done per day×Number of days
40 km=2 km/day×d
Solving for d:
d=40 km2 km/day=20 days
Final Answer
Thus, it will take 40 engineers and 40 workers 20 days to construct a 40 km road.
---
We know that:
- 20 engineers and 20 workers can construct a 20 km road in 20 days.
Total time taken = 20 days
The work done per day by 20 engineers and 20 workers:
Work per day=Total workTotal time=20 km20 days=1 km/day
Since 20 engineers and 20 workers together do 1 km of work in a day, we can express this as:
Work done by 20 engineers and 20 workers in one day=1 km
20e+20w=1 km
Dividing the entire equation by 20:
e+w=120 km
Now, we need to find out how many days it will take for 40 engineers and 40 workers to construct a 40 km road.
Let d be the number of days required.
40e+40w
We can factor out 40:
40(e+w)=40×120=2 km/day
Now, we need to find d such that:
Total work=Work done per day×Number of days
40 km=2 km/day×d
Solving for d:
d=40 km2 km/day=20 days
Thus, it will take 40 engineers and 40 workers 20 days to construct a 40 km road.
Topper's Solved these Questions
Similar Questions
If 900 persons can finish the construction of a building in 40 days, how many persons are needed to complete the construction of building in 25 days.
View SolutionWorking together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?
View Solution
Knowledge Check
If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.
A125 daysB122 daysC120 daysD116 daysP, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
A40B72C84D90P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
A1800B900C1200D1500
Anil, Dinesh and Deepak together can complete a work in 40 days. Anil and Dinesh together can complete the same work in 50 days. In how many days Deepak alone can complete the same work?
View Solution30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days :
View SolutionWorking together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?
View SolutionA, B and c can complete a piece of work in 10, 20 and 60 days respectively. Working together can complete the same work in how many days?
View SolutionA, B and C can complete a piece of work in 5, 20 and 60 days respectively. Working together, they can complete the same work in how many days ?
A, B और C किसी कार्य को क्रमशः 5, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए, वे इस कार्य को कितने दिनों में पूरा करेंगे ?
View Solution