If 20 engineers and 20 workers can together construct a 20 km road in 20 days. 40 engineers and 40 workers together construct 40 km road in how many days?

A

10

B

20

C

40

D

can’t be determined

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work done by the engineers and workers in the first scenario and then use that information to find out how many days it will take for the second scenario.

Step 1: Determine the total work done in the first scenario
We know that:
- 20 engineers and 20 workers can construct a 20 km road in 20 days.

Total work done (in km) = 20 km
Total time taken = 20 days

Step 2: Calculate the work done per day
The work done per day by 20 engineers and 20 workers:
Work per day=Total workTotal time=20 km20 days=1 km/day

Step 3: Calculate the work done by one engineer and one worker
Since 20 engineers and 20 workers together do 1 km of work in a day, we can express this as:
Work done by 20 engineers and 20 workers in one day=1 km

Let the work done by one engineer in one day be e km and the work done by one worker in one day be w km. Therefore:
20e+20w=1 km
Dividing the entire equation by 20:
e+w=120 km

Step 4: Analyze the second scenario
Now, we need to find out how many days it will take for 40 engineers and 40 workers to construct a 40 km road.

Total work required = 40 km
Let d be the number of days required.

The work done by 40 engineers and 40 workers in one day:
40e+40w
We can factor out 40:
40(e+w)=40×120=2 km/day

Step 5: Calculate the number of days required
Now, we need to find d such that:
Total work=Work done per day×Number of days
40 km=2 km/day×d
Solving for d:
d=40 km2 km/day=20 days

Final Answer
Thus, it will take 40 engineers and 40 workers 20 days to construct a 40 km road.

---

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.

    A125 days
    B122 days
    C120 days
    D116 days
  • P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?

    A40
    B72
    C84
    D90
  • P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?

    A1800
    B900
    C1200
    D1500